Table T5. Casing depths, drilling depths, and significant events, Expedition 348.

Event Time, Date
(h UTC, 2013/2014)
Measured depth
(MD; mBRT)
Measured depth
(MD; mbsf)
True vertical depth
(TVD; mbsf)
Remarks
Sea level   1967.50 0.00 0.00  
36 inch casing   2021.40 53.90 53.90  
20 inch casing   2827.80 860.30 860.30  
Lithologic Unit I/II boundary   2167.50 200.00 200.00  
Lithologic Unit II/III boundary   2843.00 875.50 875.50  
Lithologic Unit III/IV boundary   2943.00 975.50 975.50  
Lithologic Unit IV/V boundary   3633.00 1665.50 1664.40  
TD Hole C0002F   3973.00 2005.50 2005.50  
Hole C0002F side track 0815, 4 Nov 2845.00 877.50 877.50  
Hole C0002N 0815, 4 Nov 2827.80 860.30 860.30  
Borehole conditioning (top) 1030, 6 Nov 2805.90 838.40 838.40 *1205–1221 mbsf; ~15 h
Borehole conditioning (bottom) 2245, 5 Nov 3186.50 1219.00 1217.90 *1205–1221 mbsf; ~15 h
WOW #1 2115, 7 Nov 3645.00 1677.50 1676.40 POOH to 1939.8 mBRT
WOW #1 2200, 8 Nov 3645.00 1677.50 1676.40 *1662–1678 mbsf; ~28.5 h
Lost signal 0815, 9 Nov 3823.80 1856.30 1855.20  
WOW #2 0000, 10 Nov 3976.00 2008.50 2007.40 POOH to surface
WOW #2 2215, 11 Nov 3976.00 2008.50 2007.40 *1992–2008 mbsf; ~50 h
Mud loss #1 2345, 11 Nov 4004.00 2036.50 2035.40 *2022–2038 mbsf; ~8.5 h
Mud loss #1 0000, 12 Nov 3995.50 2028.00 2026.90 *2022–2038 mbsf; ~8.5 h
Mud loss #2 1100, 12 Nov 4085.00 2117.50 2116.40  
Hole C0002N TD 0115, 13 Nov 4297.50 2330.00 2328.90 859.5–2329.3 (1962.6–2008.5 overlap zone) mbsf; logged interval
Hole C0002N 13-3/8 inch casing 0645, 22 Nov 3977.50 2010.00 2008.90 2013 m total length
13-3/8-inch casing TOC   3320.00 1352.50 1351.41  
Bridge plug 1745, 7 Dec 3916.50 1949.00 1947.90  
Top of DC fish   3928.08 1960.58 1959.50  
Window top   3904.00 1936.50 1935.40  
Window bottom   3912.63 1945.13 1944.00  
Hole C0002P sidetrack top 0000, 15 Dec 3904.00 1936.50 1935.40  
LOT #1 0630, 15 Dec 3922.00 1954.50 1953.40 1130 psi (7.79 Mpa)
LOT #2 0700, 15 Dec 3922.00 1954.50 1953.40 1280 psi (8.83 Mpa)
WOW #3 18–20, Dec 4035.20 2067.70 2066.50  
Bottom of kickoff 1400, 20 Dec 4075.00 2107.50 2106.30  
Core prep 20–22, Dec 4130.50 2163.00 2161.70  
Top RCB coring 2045, 22 Dec 4130.50 2163.00 2161.70  
Fault zone   4172.50 2205.00   Zone width: 2204.9–2205.8 mbsf
Bottom of RCB coring 1745, 24 Dec 4186.00 2218.50 2216.60  
Open hole (top) 1200, 27 Dec 4130.00 2162.50 2161.20 *2163–2218.5 mbsf; >66.25 h
Open hole (bottom) 1800, 27 Dec 4186.00 2218.50 2217.10 *2163–2218.5 mbsf; >66.25 h
TD 12-1/4 inch LWD 0700, 1 Jan 5026.00 3058.50 3056.60 2163.5–3058.5 mbsf; logged interval
Top of open hole 14½ inch 2230, 2 Jan 3928.00 1960.50 1959.40  
Stuck pipe 1340, 11 Jan 4928.00 2960.50 2959.50 2960.5 mbsf; ~1.75 h
Stuck pipe 0400, 14 Jan 4932.00 2964.50 2963.50 2964.5 mbsf; ~17 h; pressure stabilized at 15.2 Mpa
Hole C0002P 11¾ inch casing 0630, 18 Jan 4890.00 2922.50 2920.65 1007.18 m total length
LOT #3 1945, 19 Jan       After diverter, before CRT; 650 psi (4.48 Mpa) and 530 psi (3.65 Mpa)
TD 14-1/2 inch hole   4927.50 2960.00 2958.14  

* = depth intervals with long exposure time before LWD tools were able to log after initial drilling. TD = total depth, WOW = waiting on weather, TOC = top of casing/cement, DC = drill collar, LOT = leak-off test, RCB = rotary core barrel, LWD = logging while drilling, POOH = pull out of hole, CRT = casing running tool.