Table T1. Operations summary, Site C0002.

Hole C0002G
Latitude: 33°18.0130′N
Longitude: 136°38.1500′E
Water depth (m): 1936
Seafloor (m): 1966 DRF (1937.5 mbsl)
20 inch conductor pipe shoe (m): 2007 DRF (41 mbsf)
9-5/8 inch casing screen interval (m): 2723–2746 DRF (757–780 mbsf)
9-5/8 inch casing shoe (m): 2854 DRF (888 mbsf)
TD (m): 2946 DRF (980 mbsf)
Operation Start Depth DSF (m) Comments
Date
(2010)
Local time
(h)
Top Bottom
Hole C0002G     0 980  
Prep tool, rig up, and RIH 13 Nov 0030     Lower Big Head transducers and check transponders
Transit to LCA 13 Nov 0130     Make up jetting BHA, prepare 20 inch conductor casing
Run 20 inch conductor casing 13 Nov 0615     Pick up 20 inch casing shoe jetting joint
    1100     Pick up Jetting BHA and run into 20 inch casing
Run mudmat into moonpool 13 Nov 1100      
Pick up and secure mudmat on working cart 13 Nov 1300     Current increase, so necessary to recover mudmat
Move vessel 21 nmi northwest 13 Nov 1330     Reach LCA at 1800 h
Resume running 20 inch casing to 110 m DRF 13 Nov 1800     Dove ROV to confirm jet sub projection
Begin attaching and terminating anti-VIV ropes 13 Nov 2200      
Resume running 20 inch casing to 1513 m DRF 13 Nov 2330      
Run 20 inch conductor casing 14 Nov 0330     Run to 1860 m DRF while attaching ropes
Dive ROV 14 Nov 1745      
Monitor drill string for VIV 14 Nov 2030     Drifting to Site C0002
Resume running 20 inch casing 15 Nov 1000     Run to 1956 m DRF
Tag seafloor, confirm hole position 15 Nov 1215     ROV survey of seabed
Jet-in 20 inch casing 15 Nov 1300 0 40.9 Jet to 40.9 mbsf
Release cart 15 Nov 1630      
Pick up BHA to 1970 m DRF 15 Nov 1730      
POOH jetting assembly to 1156 m DRF 15 Nov 1830     Begin removing anti-VIV ropes
Recover ROV on deck 15 Nov 2130      
Finish anti-VIV ropes at 1430 m DRF 15 Nov 2315      
POOH jetting assembly to surface 16 Nov 0330      
Make up lower guide horn in moonpool 16 Nov 1045      
Make up and RIH 12-1/4 inch BHA to 92 m DRF 16 Nov 1900      
Run shallow test for LWD and MWD 16 Nov 2100      
Start drifting 16 Nov 2245      
RIH to 1800 m DRF 17 Nov 0415     RIH from 92 to 1800 m DRF while drifting to Hole C0002G
Drift to Hole C0002G 17 Nov 0815      
Run to 1965 m DRF 17 Nov 0945      
Reenter wellhead 17 Nov 0945      
Ream to 2007 m DRF 17 Nov 1030      
Drill 12-1/4 inch LWD hole to 2267 m DRF 17 Nov 2400 0 301 ROP 40 m/h
Drill 12-1/4 inch LWD hole to 2573 m DRF 18 Nov 1145 0 607 ROP 40 m/h. Pump 5 m3 Hi-Vis mud every half-stand
Sweep and circulate to clean hole 18 Nov 1230     Hi-Vis mud 10 m3
Short trip to 20 inch casing shoe 18 Nov 1430      
Run back to bottom 18 Nov 1830      
Resume drilling 12-1/4 inch hole to 2675 m DRF 18 Nov 2400 0 709 Below 2620 m DRF ROP reduced to 30 m/h
Drill 12-1/4 inch LWD hole to 2858 m DRF 19 Nov 1045 0 892 ROP controlled at 30 m/h
Sweep Hi-Vis mud and circulate to clean hole 19 Nov 1145     Sweep 10 m3
Spot 60 m3 Hi-Vis mud 19 Nov 1230      
POOH to 1810 m DRF 19 Nov 1530      
ROV on deck 19 Nov 1640      
Resume POOH while drifting 19 Nov 2015      
POOH to rig floor 20 Nov 0100     Lay out 12-1/4 inch BHA
Make up and RIH 10-5/8 inch LWD BHA 20 Nov 0800     Run to 1800 m DRF
Move to location, dive ROV 1 nmi from Hole C0002G 20 Nov 1030      
Resume RIH to 1993 m DRF 20 Nov 1130      
RIH to 2830 m DRF 20 Nov 1530      
Relog from 2788 to 2804 and 2833 to 2858 m DRF 20 Nov 1900      
Drill 10-5/8 inch LWD hole to 2912 m DRF 20 Nov 2400 0 946 Average ROP 22.1 m/h
Drill 10-5/8 inch LWD hole to 2946 m DRF 21 Nov 0230 0 980 Average ROP 14.6 m/h
Circulate to clean hole, Hi-Vis mud 21 Nov 0445      
POOH to 2862 m DRF, relog LWD from 2859 m DRF 21 Nov 0600     LWD data merge for 2859–2830 m DRF LWD run
Trip to 2500 m DRF 21 Nov 0715      
Ream to bottom 21 Nov 0900      
Circulate bottoms up 21 Nov 1200     Sweep Hi-Vis mud, 10 m3
Run back to bottom 21 Nov 1815     No excess drag
Sweep out Hi-Vis mud 10 m3 21 Nov 1900      
Spot Hi-Vis mud 104 m3 21 Nov 2015      
POOH to 1870 m DRF 21 Nov 2400      
Continue POOH 10-5/8 inch LWD BHA 22 Nov 0615      
Prepare for running casing 22 Nov 0845      
Run 9-5/8 inch casing to 130 m DRF 22 Nov 1730      
Replace PS-30 to manual slip 22 Nov 1830      
Drift to Hole C0002G 22 Nov 2300      
Resume running 9-5/8 inch casing to 885 m DRF 22 Nov 2315      
Run inner string to float collar 23 Nov 0300      
Pick up DP S150 with XO sub 23 Nov 0345      
Dive ROV 23 Nov 0510      
Connect casing hanger running tool to 9-5/8 inch casing hanger 23 Nov 0530      
Break circulation with leak test 23 Nov 0600      
Recover ROV on deck 23 Nov 0625      
Run 9-5/8 inch casing to 1360 m DRF 23 Nov 0715      
Run 9-5/8 inch casing to 1830 m DRF 23 Nov 2000     Run with anti-VIV ropes
Install upper guide horn 23 Nov 2300      
Drift to Hole C0002G 23 Nov 2400      
Drift to Hole C0002G 24 Nov 2400     Drifting for 24 h
Drift to Hole C0002G 25 Nov 0215     No VIV observed
RIH to 1956 m DRF, prepare to reenter hole 25 Nov 0300      
RIH to 2853 m DRF 25 Nov 0530      
Hook up cementing line 25 Nov 0600      
Land 18-3/4 inch and 9-5/8 inch casing hanger on wellhead 25 Nov 0615      
Cement 9-5/8 inch casing 25 Nov 0930      
Release casing hanger running tool 25 Nov 0945      
POOH to 1918 m DRF 25 Nov 1215      
Move rig to 50 m offset 25 Nov 1230      
Drop sponge ball and circulate 25 Nov 1245      
Recover ROV on deck 25 Nov 1330      
Rig down upper guide horn 25 Nov 1530      
POOH to 1795 m DRF 25 Nov 1600      
POOH to 1360 m DRF, removing ropes 25 Nov 2045      
Continue POOH to 265 m DRF 25 Nov 2400      
Continue POOH to surface 26 Nov 0045      
Pick up cement stand and inspect cement head 26 Nov 0200     Observe wiper plug stuck above drop indicator
Move to Shimizu Port 26 Nov 0200      
Standby 7 nmi off Shimizu Port 27 Nov 0030      
Port call 27 Nov 0700      
Leave Shimizu Port 27 Nov 2000      
Move to 7 nmi upstream of Hole C0002G 28 Nov 1730      
Stop vessel set DP mode, install ROV cursor 28 Nov 2030      
Run drill-out cement assembly to 1143 m DRF 28 Nov 2030      
Continue to RIH drill-out assembly to 1860 m DRF 29 Nov 0130      
Dive ROV 29 Nov 0315      
Drift to Hole C0002G 29 Nov 0430      
RIH to 2826 m DRF 29 Nov 0730      
Drill out cement 29 Nov 0830     Ream around float shoe three times. Float shoe bottom 2853 m DRF
Wash down to 2937 m DRF 29 Nov 0930      
Sweep 10 kL Hi-Vis mud pill and spot 15 kL of Hi-Vis mud pill on bottom 29 Nov 1030      
Short trip to 9-5/8 inch float shoe 29 Nov 1100      
RIH to 2943 m DRF 29 Nov 1215      
Pump 90 spm and sweep out with 10 m3 Hi-Vis mud 29 Nov 1315      
Pick up to 2930 m DRF. Spot NaCl and protect zone 29 Nov 1530      
Drop Churchill drift gauge at 2930 m DRF and POOH to wellhead 29 Nov 1715      
POOH to surface with drifting 29 Nov 2200      
Move vessel 20 nmi northwest from Hole C0002G 29 Nov 2400      
Pick up CORK running tool and make up with pup joint and XO 30 Nov 0500      
Install two wiper plugs and rack cement stand 30 Nov 0645      
Rig down upper guide horn 30 Nov 0730      
Prepare for running completion assembly 30 Nov 1000      
Run completion assembly 30 Nov 2300      
Continue to run completion assembly 1 Dec 0000     Run completion assembly to 49 m DRF
Connect and terminate 3 cables, flatpack, and thermistor string 1 Dec 0700      
Run 2 joints of 3.5 inch tubing, attaching 4 centralizers per joint 1 Dec 2145      
Run completion assembly from 90 to 206 m DRF 2 Dec 0000      
Pick up and make up swellable packer joint and 2 joints tubing 2 Dec 1400      
Install 3 electric cables and flatpack into swellable packer 2 Dec 1630      
Test 3 cables after installation into packer 2 Dec 2215      
Resume running completion assembly from 220 to 227 m DRF 2 Dec 2300      
Continue to run completion assembly to 335 m DRF 3 Dec 0000      
Troubleshoot on hydraulic unit of working cart 3 Dec 0500      
Run completion assembly from 335 to 948 m DRF 3 Dec 0830      
Take off quick lifting tool and prepare for CORK pick-up 4 Dec 0000      
Pick up CORK running tool and engage on CORK 4 Dec 0045      
Make up CORK on 3.5 inch tubing 4 Dec 0145      
Lower CORK to moonpool 4 Dec 0200      
Test 3 cables prior to termination 4 Dec 0400      
Mark and measure 3 control lines and terminate 4 Dec 0500      
Wind all cables and flatpack to winches 4 Dec 0645      
Terminate electrical cables on CORK 4 Dec 0730      
Continue termination on cables 5 Dec 0000      
Connect 3 hydraulic lines on CORK 5 Dec 0600      
Install 3 ODI connectors and cables to CORK 5 Dec 0830      
Prepare to install ROV platform 5 Dec 1400      
Drift 22 nmi to Hole C0002G 5 Dec 1530      
Install ROV platform 5 Dec 1645      
Run 1 stand of DP to 1010 m DRF 5 Dec 1945      
RIH to 1010 m DRF, install Accelerometer 1 5 Dec 2030      
RIH to 1300 m DRF, dive ROV 5 Dec 2230      
Attach 4 ropes on drill string, recover ROV 5 Dec 2245      
RIH completion assembly 1300–1417 m DRF 6 Dec 0000      
Engage ODI connectors and test 3 cables with ROV 6 Dec 0200      
Resume RIH from 1417 to 1800 m DRF 6 Dec 0430      
Continue drifting to Hole C0002G 6 Dec 0830      
Continue drifting to Hole C0002G 7 Dec 0000      
Continue drifting to Hole C0002G 8 Dec 0000      
Run completion string from 1800 to 1897 m DRF 8 Dec 0045      
Continue drifting to Hole C0002G 8 Dec 0200      
Test 3 cables by ROV 8 Dec 0430      
Check completion assembly condition 8 Dec 0515      
Resume RIH to 1963 m DRF 8 Dec 0615      
Adjust vessel position and reenter wellhead 8 Dec 0845      
Resume RIH to 2904 m DRF 8 Dec 0915      
Pick up and make up cement stand connect to HPS 8 Dec 1945      
Land CORK head on wellhead 8 Dec 2015      
Connect ODI connector and test tiltmeter and strainmeter 8 Dec 2015      
Pump 64 m3 of seawater 8 Dec 2215      
Continue to mix cement slurry, total 44 bbl 9 Dec 0045      
Complete cementing 9 Dec 0230      
Set unjay stopper and release CORK running tool 9 Dec 0330      
Rack back cement stand, move vessel 30 nmi south 9 Dec 0415      
Drop sponge ball and circulation 9 Dec 0430      
POOH CORK running tool to 1720 m DRF 9 Dec 0500      
Recover ROV on deck 9 Dec 0750      
Recover CORK running tool on surface 9 Dec 1355      
Dive ROV for pressure unit testing 9 Dec 1825      
Test pressure unit 9 Dec 1910      
Recover ROV on deck 9 Dec 0750      
Dive ROV to recover transponders 9 Dec 1825      
Recover ROV on deck 9 Dec 2030      

DRF = drilling depth below rig floor, mbsl = meters below sea level, mbsf = meters below seafloor, DSF = drilling depth below seafloor. TD = total depth. RIH = run in hole, POOH = pull out of hole. LCA = low-current area. VIV = vortex-induced vibration. ROV = remotely operated vehicle. LWD = logging while drilling, MWD = measurement while drilling. BHA = bottom-hole assembly. DP = dynamic positioning. XO = crossover. ODI = Ocean Design, Inc. bbl = 42 gallon barrel. CORK = circulation obviation retrofit kit.