Table T14. Logging operations summary, Hole U1382A.

Date
(2011)
Time
(h)
Activity
9 Oct 0215 Downhole logging operations start
9 Oct 0317 AMC I tool string run into hole
9 Oct 0534 Wireline heave compensation optimization performed with tool string entirely in casing
9 Oct 0638 Begin downlog at 4590.1 m WRF
9 Oct 0650 Reach total depth of 4700 m WRF
9 Oct 0654 Begin uplog
9 Oct 0718 Power cycle issue (possible short encountered); tool string power loss (4620 m WRF)
9 Oct 0720 Logging aborted and tool brought back to surface
9 Oct 1110 AMC I tool string rigged down
9 Oct 1218 FMS-HNGS tool string rigged up
9 Oct 1221 FMS-HNGS run into hole
9 Oct 1452 Begin downlog at 4490.8 m WRF; wireline heave compensator was not used because of low heave conditions
9 Oct 1517 Tool string reached total depth at 4703.1 m WRF
9 Oct 1519 Begin first pass
9 Oct 1535 End first pass
9 Oct 1536 Run tool string back down to total depth
9 Oct 1546 Begin second pass
9 Oct 1603 Tool string not able to reenter pipe (4558 m WRF)
9 Oct   Attempted to drop tool string back down; opened and closed calipers numerous times
9 Oct 1612 Preparations made to “carwash” the tool string into the pipe
9 Oct 1812 FMS-HNGS tool string successfully reenters pipe
9 Oct 2110 Tool string back to surface (some visible damage to FMS Pad 3)
9 Oct 2153 FMS-HNGS rigged down and logging operations concluded

AMC I = adapted microbiology combination I, FMS = Formation MicroScanner, HNGS = Hostile Environment Natural Gamma Ray Sonde. Time is reported as ship local (UTC – 3 h).