Table T1. Summary of basement operations completed at Site U1383. Operations included (A) a jet-in test in Hole U1383A; (B) installing a reentry cone with 16 inch casing, installing 10.75 inch casing, drilling a 14.75 inch hole below the casing with a bit failure, and installing a remotely operated vehicle (ROV) platform in Hole U1383B; and (C) installing a reentry cone and two casing strings, rotary core barrel (RCB) coring to 331.5 mbsf, downhole logging and packer experiments, and installing a multilevel subseafloor borehole observatory (CORK) in Hole U1383C.

Operational task Start End Task time
Date
(2011)
Time
(h)
Date
(2011)
Time
(h)
Hours Days
(A) Hole U1383A: jet-in test at proposed Site NP-2
Make up 18.5 inch tricone bit            
Handle BHA (will take 1 h) 12 Oct 1230 12 Oct 1400 1.50 0.06
Trip: surface to mudline, ±1 h in 4425 m of water 12 Oct 1400 12 Oct 2045 6.75 0.28
Handle camera (will take 0.5 h) 12 Oct 2045 12 Oct 2100 0.25 0.01
Pick up top drive and space out drill pipe (will take 0.75 h) 12 Oct 2100 12 Oct 2145 0.75 0.03
Drill string tag (will take 0.5 h) 12 Oct 2145 12 Oct 2215 0.50 0.02
Begin to recover camera frame            
Record SCRs and space out for jet-in test (will take 0.25 h); spud Hole U1383A at 2240 h 12 Oct 2215 12 Oct 2245 0.50 0.02
Jet-in test (will take 6 h) to 4461 mbrf (36 mbsf); very firm with max weight down and 120 spm (ROP ~1.0 m/h) 12 Oct 2245 13 Oct 0200 3.25 0.14
Pull out of hole (will take 0.5 h); top drive clears seafloor at 0221 h 13 Oct 0200 13 Oct 0245 0.75 0.03
Set back top drive (will take 0.25 h) 13 Oct 0245 13 Oct 0300 0.25 0.01
Trip: depth to surface: from (mudline) 0 mbsf to surface, plus 0 h in 4425 m of water 13 Oct 0300 13 Oct 0900 6.00 0.25
Handle BHA (will take 1 h) 13 Oct 0900 13 Oct 0930 0.50 0.02
Bit clears rig floor at 0931 h; end of Hole U1383A            
Hole U1383A totals: 12 Oct 1230 13 Oct 0930 21.00 0.88
(B) Hole U1383B: install reentry cone and 20 inch casing
Reentry cone (will take 2 h) 13 Oct 0930 13 Oct 1015 0.75 0.03
Run 20 inch casing            
Rig up/down for casing (will take 1 h) 13 Oct 1015 13 Oct 1030 0.25 0.01
Assemble 20 inch casing 13 Oct 1030 13 Oct 1245 2.25 0.09
Rig up/down for casing (will take 0.25 h) 13 Oct 1245 13 Oct 1315 0.50 0.02
Make up casing running tool (will take 0.5 h) 13 Oct 1315 13 Oct 1315 0.00 0.00
Lower 20 inch casing and latch into reentry funnel (will take 0.5 h) 13 Oct 1315 13 Oct 1345 0.50 0.02
Release running tool, pull back to rig floor, and RIH with bottom section of BHA (will take 0.5 h) 13 Oct 1345 13 Oct 1415 0.50 0.02
RIH and latch running tool into reentry cone (will take 0.5 h) 13 Oct 1415 13 Oct 1500 0.75 0.03
Pick up reentry cone and open moonpool doors/lower reentry cone (will take 0.25 h) 13 Oct 1500 13 Oct 1515 0.25 0.01
Reentry funnel in water at 1522 h            
Handle BHA (will take 1 h) 13 Oct 1515 13 Oct 1545 0.50 0.02
Trip: surface to mudline, plus 0 h in 4425 m of water 13 Oct 1545 13 Oct 2330 7.75 0.32
Deploy camera (will take 0.5 h) 13 Oct 2330 14 Oct 0000 0.50 0.02
Pick up top drive and space out drill pipe (will take 1 h) 14 Oct 0000 14 Oct 0100 1.00 0.04
Spud Hole U1383B at 0100 h            
Jet-in casing (will take 5 h) 14 Oct 0100 14 Oct 0500 4.00 0.17
Repair mud pump #2; sheared pin in the pony rod (will take 0.5 h) 14 Oct 0500 14 Oct 0530 0.50 0.02
Resume jetting-in casing (will take 1 h) 14 Oct 0530 14 Oct 0730 2.00 0.08
POOH with 20 inch casing to clear seafloor, and move 50 m at 045° (will take 0.75 h) 14 Oct 0730 14 Oct 0815 0.75 0.03
Stop jet-in of 20 inch casing at 0728 h; clear seafloor at 0730 h            
Resume jet-in of 20 inch casing (will take 2 h); spud at 0810 h 14 Oct 0815 14 Oct 1015 2.00 0.08
Release running tool (will take 1 h); release at 1035 h 14 Oct 1015 14 Oct 1030 0.25 0.01
Set back top drive (will take 0.5 h) 14 Oct 1030 14 Oct 1100 0.50 0.02
Trip: mudline to surface, ±1 h in 4425 m of water 14 Oct 1100 14 Oct 1715 6.25 0.26
Recover camera (will take 0.5 h) 14 Oct 1715 14 Oct 1730 0.25 0.01
Handle BHA (will take 1 h) 14 Oct 1730 14 Oct 1815 0.75 0.03
De-torque and lay out casing running tool and lay out drill collars pups (will take 1 h) 14 Oct 1815 14 Oct 1915 1.00 0.04
Hole U1383B: drill out 18.5 inch hole for 16 inch casing
Change out bit jets in 18.5 inch tricone bit (will take 0.5 h) 14 Oct 1915 14 Oct 1945 0.50 0.02
Handle BHA (will take 0.75 h) 14 Oct 1945 14 Oct 2015 0.50 0.02
Trip: surface to 2978 mbrf (will take 5 h) 14 Oct 2015 15 Oct 0115 5.00 0.21
Deploy camera (will take 0.5 h) 15 Oct 0115 15 Oct 0130 0.25 0.01
Slip/Cut drill line at 100 stands (will take 1.5 h) 15 Oct 0130 15 Oct 0245 1.25 0.05
Trip from 2978 mbrf to mudline (will take 2 h) 15 Oct 0245 15 Oct 0515 2.50 0.10
Maneuver ship for reentry (will take 0.5 h); reenter Hole U1383B at 0518 h 15 Oct 0515 15 Oct 0515 0.00 0.00
Recover camera from seafloor 15 Oct 0515 15 Oct 0645 1.50 0.06
Trip to casing shoe and pick up top drive while recovering camera frame            
Trip: depth to depth: from (mudline) 0 to 40 mbsf, plus 0 h in 4425 m of water 15 Oct 0645 15 Oct 0645 0.00 0.00
Pick up top drive and space out drill pipe (will take 0 h) 15 Oct 0645 15 Oct 0645 0.00 0.00
RIH and tag bottom at 0704 h (will take 0.25 h) 15 Oct 0645 15 Oct 0700 0.25 0.01
Drill ahead 18.5 inch hole in sediment: from 40 to 53 mbsf at 15 m/h 15 Oct 0700 15 Oct 0730 0.50 0.02
Basement contact at 53 mbsf at 0723 h            
Drill ahead 18.5 inch hole in basement: from 53 to 68 mbsf at 2 m/h 15 Oct 0730 15 Oct 1630 9.00 0.38
Circulation (will take 1 h) 15 Oct 1630 15 Oct 1700 0.50 0.02
Wiper trip: from 68 mbsf to 35 mbsf and back 15 Oct 1700 15 Oct 2045 3.75 0.16
Wiper trip 1: 4 m soft fill on bottom; circulate mud sweep            
Wiper trip 2: 2 m soft fill; circulate mud sweep            
Wiper trip 3: 2 m soft fill again; circulate mud sweep            
End of hole conditioning: 1 m soft fill—easily washed            
Trip: depth to depth: from 68 to 35 mbsf, plus 0 h in 4425 m of water 15 Oct 2045 15 Oct 2100 0.25 0.01
Set back top drive (will take 0.5 h) 15 Oct 2100 15 Oct 2115 0.25 0.01
Trip: depth to surface: from 35 mbsf to surface, ±0.5 h in 4425 m of water 15 Oct 2115 16 Oct 0430 7.25 0.30
Handle BHA (will take 1 h) 16 Oct 0430 16 Oct 0500 0.50 0.02
Hole U1383B: install 16 inch casing
Lay out bit sub/float valve, make up casing running tool with drill collars, rack back stand (will take 0.5 h) 16 Oct 0500 16 Oct 0530 0.50 0.02
Rig up/down for casing (will take 2 h) 16 Oct 0530 16 Oct 0615 0.75 0.03
Assemble 16 inch casing 16 Oct 0615 16 Oct 0745 1.50 0.06
Make up casing running tool with 16 inch casing hanger and replace master bushings (will take 1 h) 16 Oct 0745 16 Oct 0815 0.50 0.02
Handle BHA (will take 0.5 h) 16 Oct 0815 16 Oct 0830 0.25 0.01
Trip: surface to mudline, plus 0 h in 4425 m of water 16 Oct 0830 16 Oct 1445 6.25 0.26
Deploy camera (will take 0.25 h) 16 Oct 1445 16 Oct 1500 0.25 0.01
Maneuver ship for reentry (will take 0.5 h); reenter at 1524 h 16 Oct 1500 16 Oct 1530 0.50 0.02
Trip: mudline to depth: from 0 to 50 mbsf, plus 0.5 h 16 Oct 1530 16 Oct 1600 0.50 0.02
Unable to pass basement contact; work drill string/offset ship (will take 3 h) 16 Oct 1600 16 Oct 1945 3.75 0.16
Work casing shoe to ~3.0 m into basement; hole apparently slightly deviated            
Decision made to POOH and shorten casing length by 5.0 m, placing 16 inch casing shoe ~1.0 m into basement (original target was 5–6 m into basement)            
Trip: depth to surface: from 50 mbsf to surface, ±1.5 h in 4425 m of water 16 Oct 1945 17 Oct 0300 7.25 0.30
Handle BHA and remove casing running tool from casing hanger (will take 0.5 h) 17 Oct 0300 17 Oct 0330 0.50 0.02
Break out and lay out hanger joint (will take 1 h) 17 Oct 0330 17 Oct 0515 1.75 0.07
Break out and lay out 2 additional joints of casing (will take 1.25 h) 17 Oct 0515 17 Oct 0630 1.25 0.05
Shorten casing shoe joint by 5.0 m and weld on new casing shoe (will take 1.5 h) 17 Oct 0630 17 Oct 0800 1.50 0.06
Make up remaining casing joints (will take 1.5 h) 17 Oct 0800 17 Oct 0930 1.50 0.06
Make up casing running tool with 16 inch casing hanger (will take 0.5 h) 17 Oct 0930 17 Oct 0945 0.25 0.01
Handle BHA (will take 0.25 h) 17 Oct 0945 17 Oct 1000 0.25 0.01
Trip: surface to mudline, ±1.5 h in 4425 m of water 17 Oct 1000 17 Oct 1500 5.00 0.21
Handle camera (will take 0.5 h) 17 Oct 1500 17 Oct 1530 0.50 0.02
Maneuver ship for reentry (will take 0.5 h); reenter at 1537 h 17 Oct 1530 17 Oct 1545 0.25 0.01
Trip: mudline to depth: from 0 to 50 mbsf, plus 0.5 h 17 Oct 1545 17 Oct 1600 0.25 0.01
Pick up top drive and space out drill pipe (will take 0.5 h) 17 Oct 1600 17 Oct 1615 0.25 0.01
Land casing (will take 1 h) 17 Oct 1615 17 Oct 1630 0.25 0.01
Cement casing shoe (will take 2 h) 17 Oct 1630 17 Oct 1745 1.25 0.05
Release cone/casing hanger (will take 0.5 h); release casing at 1743 h 17 Oct 1745 17 Oct 1745 0.00 0.00
Circulation (will take 1 h) 17 Oct 1745 17 Oct 1845 1.00 0.04
Set back top drive (will take 0.5 h) 17 Oct 1845 17 Oct 1915 0.50 0.02
Recover camera (will take 0.5 h) 17 Oct 1915 17 Oct 1945 0.50 0.02
Trip: mudline to surface, plus 0 h in 4425 m of water 17 Oct 1945 18 Oct 0115 5.50 0.23
Handle BHA (will take 1 h) 18 Oct 0115 18 Oct 0145 0.50 0.02
De-torque casing running tool and lay out to rig floor (will take 0.5 h) 18 Oct 0145 18 Oct 0200 0.25 0.01
Hole U1383B: drill 14.75 inch hole for 10.75 inch tricone bit and drill out for 10.75 inch casing
Handle BHA (will take 1 h) 18 Oct 0200 18 Oct 0330 1.50 0.06
Deploy camera (will take 0.5 h) 18 Oct 0330 18 Oct 0400 0.50 0.02
Trip: surface to mudline, ±1.25 h in 4425 m of water 18 Oct 0400 18 Oct 1015 6.25 0.26
Slip/Cut drill line (will take 1.5 h) 18 Oct 1015 18 Oct 1200 1.75 0.07
Maneuver ship for reentry (will take 0.5 h); reenter at 1210 h 18 Oct 1200 18 Oct 1215 0.25 0.01
Trip: mudline to depth: from 0 to 59 mbsf, plus 1 h 18 Oct 1215 18 Oct 1300 0.75 0.03
Recover camera (will take 0.5 h) 18 Oct 1300 18 Oct 1330 0.50 0.02
Tag cement at 49 mbsf            
Pick up top drive and space out drill pipe (will take 1 h) 18 Oct 1330 18 Oct 1345 0.25 0.01
Take slow circulating rates (will take 0.75 h) 18 Oct 1345 18 Oct 1415 0.50 0.02
Drill ahead (drill out cement/shoe): from 59 to 69 mbsf at 3 m/h 18 Oct 1415 18 Oct 1500 0.75 0.03
Break though at 1502 h at 57 mbsf            
On-bottom drilling at 1520 h            
Drill ahead: from 69 to 84 mbsf at 1.4 m/h (adjusted ROP to reflect actual time required during first drilled interval of 15 m) 18 Oct 1500 19 Oct 0145 10.75 0.45
Drill ahead: from 84 to 89 mbsf at 1.4 m/h 19 Oct 0145 19 Oct 0515 3.50 0.15
Wiper trip: from 89 mbsf to 54 mbsf and back 19 Oct 0515 19 Oct 0715 2.00 0.08
Hole problems; bit not advancing (will take 2.75 h) 19 Oct 0715 19 Oct 1000 2.75 0.11
Set back top drive (will take 0.5 h) 19 Oct 1000 19 Oct 1030 0.50 0.02
Trip: depth to surface: from 89 mbsf to surface, ±1.5 h in 4425 m of water 19 Oct 1030 19 Oct 1700 6.50 0.27
Clear seafloor at 1050 h            
Handle BHA (will take 1 h) 19 Oct 1700 19 Oct 1745 0.75 0.03
Damaged bit cleared rig floor at 1750 h, ending Hole U1383B            
Hole U1383B totals: 13 Oct 0930 19 Oct 1745 152.25 6.34
(C) Hole U1383C: re-start deep CORK observatory installation; install reentry cone with 16 inch casing
Inspect bit; found 2 of 3 bit shanks/cutters missing and third damaged (will take 0.25 h) 19 Oct 1745 19 Oct 1800 0.25 0.01
Hold meeting to discuss operational options (will take 0.5 h) 19 Oct 1800 19 Oct 1830 0.50 0.02
Determine low likelihood that hole can be salvaged; decision made to restart hole with new reentry installation            
Assemble new reentry cone and prepare new 16 inch conductor casing shoe joint (will take 12 h) 19 Oct 1830 20 Oct 0630 12.00 0.50
Deploy reentry cone and 16 inch conductor casing            
Reentry cone (will take 0 h) 20 Oct 0630 20 Oct 0630 0.00 0.00
Handle BHA (will take 0 h) 20 Oct 0630 20 Oct 0630 0.00 0.00
Rig up/down for casing (will take 0.75 h) 20 Oct 0630 20 Oct 0700 0.50 0.02
Assemble 16 inch casing 20 Oct 0700 20 Oct 0800 1.00 0.04
Rig up/down for casing (will take 0 h) 20 Oct 0800 20 Oct 0800 0.00 0.00
Make up casing running tool (will take 0.5 h) 20 Oct 0800 20 Oct 0830 0.50 0.02
Lower 16 inch casing and latch into reentry funnel (will take 0.25 h) 20 Oct 0830 20 Oct 0845 0.25 0.01
Release running tool from reentry cone (will take 0.25 h) 20 Oct 0845 20 Oct 0900 0.25 0.01
Make up BHA below running tool (will take 1 h) 20 Oct 0900 20 Oct 1000 1.00 0.04
Lower and make up running tool in reentry cone (will take 0.5 h) 20 Oct 1000 20 Oct 1015 0.25 0.01
Pick up reentry cone and open moonpool doors/lower reentry cone (will take 0.75 h) 20 Oct 1015 20 Oct 1030 0.25 0.01
Pick up tapered drill collar and 2 stands of 5.5 inch transition drill pipe (will take 0.75 h) 20 Oct 1030 20 Oct 1100 0.50 0.02
Fill pipe as required/deploy camera at 70 stands during pipe trip (will take 0.5 h) 20 Oct 1100 20 Oct 1130 0.50 0.02
Trip: surface to mudline, ±1.25 h in 4425 m of water 20 Oct 1130 20 Oct 1815 6.75 0.28
Pick up top drive and space out drill pipe (will take 0.75 h) 20 Oct 1815 20 Oct 1900 0.75 0.03
Spud Hole U1383C at 1900 h            
Jet-in casing (will take 2.75 h) 20 Oct 1900 20 Oct 2130 2.50 0.10
Release running tool (will take 0.25 h); release at 2130 h 20 Oct 2130 20 Oct 2130 0.00 0.00
POOH with top drive (will take 0.25 h) 20 Oct 2130 20 Oct 2145 0.25 0.01
Set back top drive (will take 0.5 h) 20 Oct 2145 20 Oct 2215 0.50 0.02
Trip: mudline to surface, ±1.75 h in 4425 m of water 20 Oct 2215 21 Oct 0415 6.00 0.25
Recover camera (will take 0.25 h) 21 Oct 0415 21 Oct 0430 0.25 0.01
Handle BHA, de-torque and lay out casing running tool, and lay out drill collars pups (will take 1 h) 21 Oct 0430 21 Oct 0600 1.50 0.06
Hole U1383C: drill out 14.75 inch hole for 10.75 inch casing
Make up 14.75 inch triton bit (will take 0.5 h) 21 Oct 0600 21 Oct 0630 0.50 0.02
Handle BHA (will take 0.5 h) 21 Oct 0630 21 Oct 0700 0.50 0.02
Trip: surface to mudline, ±1 h in 4425 m of water 21 Oct 0700 21 Oct 1345 6.75 0.28
Deploy camera (will take 0.5 h) 21 Oct 1345 21 Oct 1415 0.50 0.02
Maneuver ship for reentry (will take 0.5 h); reenter Hole U1383C at 1444 h 21 Oct 1415 21 Oct 1445 0.50 0.02
Pick up top drive and space out drill pipe (will take 0.5 h) 21 Oct 1445 21 Oct 1515 0.50 0.02
Move bit from (mudline) 0 to 35 mbsf (will take 0.5 h) 21 Oct 1515 21 Oct 1545 0.50 0.02
Handle camera (will take 0.75 h) 21 Oct 1545 21 Oct 1630 0.75 0.03
Drill ahead 14.75 inch hole in sediment: from 35 to 38 mbsf at 30 m/h 21 Oct 1630 21 Oct 1645 0.25 0.01
Basement contact at 38 mbsf at 1645 h         0.00 0.00
Drill ahead 14.75 inch hole in basement: from 38 to 69.5 mbsf at 1.3 m/h 21 Oct 1645 22 Oct 1845 26.00 1.08
Circulation (will take 1 h) 22 Oct 1845 22 Oct 1915 0.50 0.02
Wiper trip: from 69.5 mbsf to 80 mbsf and back 22 Oct 1915 22 Oct 2345 4.50 0.19
Wiper trip 1: ledge(?) at 100 m, 10 m fill on bottom; circulate to TD and pump 50 bbl mud sweep            
Wiper trip 2: no ledge and 3 m(??) fill on bottom; circulate to TD and pump 50 bbl sweep            
Wiper trip 3: apparent 7 m fill; circulate to TD and pump 80 bbl mud sweep            
Wiper trip 4: 5 m fill; circulate 80 bbl sweep            
Wiper trip 5: 2.7 m fill; POOH            
Trip: depth to mudline: 69.5 mbsf to mudline, plus 0.25 h 22 Oct 2345 23 Oct 0000 0.25 0.01
Set back top drive (will take 0.25 h) 23 Oct 0000 23 Oct 0015 0.25 0.01
Clear seafloor at 0025 h            
Trip: mudline to surface, ±1.5 h in 4425 m of water 23 Oct 0015 23 Oct 0630 6.25 0.26
Handle BHA (will take 0.75 h) 23 Oct 0630 23 Oct 0700 0.50 0.02
Bit clears rotary table at 0702 h            
Hole U1383C: install 10.75 inch casing
Make up stand with casing running tool and stand back in derrick (will take 0.5 h) 23 Oct 0700 23 Oct 0730 0.50 0.02
Rig up/down for casing (will take 0.75 h) 23 Oct 0730 23 Oct 0815 0.75 0.03
Case with 10.75 inch casing from 0 to 65 mbsf at 4 joints/h, plus 0 h 23 Oct 0815 23 Oct 0930 1.25 0.05
Make up 10.75 inch casing hanger and weld coupling (will take 0.25 h)/weld all casing couplings 23 Oct 0930 23 Oct 0945 0.25 0.01
Make up casing running tool to casing hanger/pull bushings/lower through rotary table (will take 0.5 h) 23 Oct 0945 23 Oct 1015 0.50 0.02
Make up 1 stand of 8.25 inch drill collars (will take 0.25 h) 23 Oct 1015 23 Oct 1030 0.25 0.01
Deploy camera (will take 0.5 h) 23 Oct 1030 23 Oct 1100 0.50 0.02
Trip: surface to mudline, ±1 h in 4425 m of water 23 Oct 1100 23 Oct 1600 5.00 0.21
Maneuver ship for reentry (will take 0.5 h); reenter at 1626 h 23 Oct 1600 23 Oct 1630 0.50 0.02
RIH with 10.75 inch casing            
Pick up top drive and space out drill pipe (will take 0.5 h) 23 Oct 1630 23 Oct 1700 0.50 0.02
Trip: mudline to depth: from 0 to 65 mbsf, plus 0.5 h 23 Oct 1700 23 Oct 1715 0.25 0.01
Land 10.75 inch casing hanger at 1720 h            
Work on cement pump (will take 0.5 h) 23 Oct 1715 23 Oct 1845 1.50 0.06
Cement casing shoe (will take 1.75 h); pump 20 bbl cement; attempt to leave cement 15 m above casing shoe 23 Oct 1845 23 Oct 1930 0.75 0.03
Cementing took longer than planned because of lumps in cement line; pumped 5 extra bbl            
Release cone/casing hanger (will take 0.25 h) 23 Oct 1930 23 Oct 1945 0.25 0.01
Flush drill pipe (will take 1 h) 23 Oct 1945 23 Oct 2030 0.75 0.03
Set back top drive (will take 0.5 h) 23 Oct 2030 23 Oct 2100 0.50 0.02
POOH with drill string (will take 4 h) 23 Oct 2100 24 Oct 0015 3.25 0.14
Handle camera (will take 0.5 h) 24 Oct 0015 24 Oct 0015 0.00 0.00
Slip/Cut originally scheduled at 70 stands but conducted at 82 stands because of racker breakdown            
Problem: spool valve manifold smoking; removed for repair or replacement            
Slip/Cut drill line (will take 1.5 h) 24 Oct 0015 24 Oct 0145 1.50 0.06
Racker still broke down            
Service rig and prepare core barrels 24 Oct 0145 24 Oct 0445 3.00 0.13
Spooler replaced, but now another hydraulic hose leaking and had to be replaced            
Racker repaired and operational            
POOH with drill string (will take 3 h) 24 Oct 0445 24 Oct 0800 3.25 0.14
Running tool cleared rotary table at 0825 h            
Handle BHA, de-torque and lay out casing running tool, and lay out drill collars pups (will take 1.5 h) 24 Oct 0800 24 Oct 0845 0.75 0.03
Hole U1383C: RCB coring, Bit 1
Make up RCB core barrel/center bit assembly (will take 1 h) 24 Oct 0845 24 Oct 0915 0.50 0.02
Make up RCB C-7 core bit and outer core barrel assembly (will take 1 h) 24 Oct 0915 24 Oct 0930 0.25 0.01
Space out core barrels (will take 0.5 h) 24 Oct 0930 24 Oct 0945 0.25 0.01
Install center bit (will take 0.5 h) 24 Oct 0945 24 Oct 1000 0.25 0.01
Handle BHA (will take 1 h) 24 Oct 1000 24 Oct 1030 0.50 0.02
Deploy camera (will take 0.5 h) 24 Oct 1030 24 Oct 1100 0.50 0.02
Trip: surface to mudline, ±1.5 h in 4425 m of water 24 Oct 1100 24 Oct 1600 5.00 0.21
Maneuver ship for reentry (will take 0.5 h); reenter at 1605 h (reentry lasted ~10 min) 24 Oct 1600 24 Oct 1600 0.00 0.00
Recover camera (will take 1 h) 24 Oct 1600 24 Oct 1730 1.50 0.06
Trip: mudline to depth: from 0 to 60 mbsf, plus 0 h 24 Oct 1730 24 Oct 1730 0.00 0.00
Pick up top drive and space out drill pipe (will take 0.5 h) 24 Oct 1730 24 Oct 1815 0.75 0.03
Tag cement at 1820 h; 4469.0 mbrf/43.8 mbsf (1 m higher than calculated)            
Drill out cement using RCB center bit (will take 2.25 h) 24 Oct 1815 24 Oct 2115 3.00 0.13
Broke out of cement at 4490 mbrf (64.8 mbsf), or 4.4 m below casing shoe            
Clean out rathole to total depth (will take 0.25 h) 24 Oct 2115 24 Oct 2130 0.25 0.01
Circulation (will take 1.25 h) 24 Oct 2130 24 Oct 2215 0.75 0.03
Aft core line hanging up in oil saver/switch to forward line (will take 0.75 h) 24 Oct 2215 24 Oct 2300 0.75 0.03
Change to forward core line            
Recover RCB center bit (will take 1.25 h) 24 Oct 2300 25 Oct 0000 1.00 0.04
Deploy RCB core barrel (will take 0.5 h) 25 Oct 0000 25 Oct 0030 0.50 0.02
SCR (will take 0.25 h) 25 Oct 0030 25 Oct 0030 0.00 0.00
Clean out hole to total depth at 70 mbsf (will take 1 h) 25 Oct 0030 25 Oct 0130 1.00 0.04
Move bit from 60 to 70 mbsf (will take 0 h) 25 Oct 0130 25 Oct 0130 0.00 0.00
RCB bit Run 1 (195 m; 58 bit rotating hours)            
ROP taken from Site U1382 rate for RCB to 200 mbsf            
Cut RCB Core 336-U1383C-2R (will take 4 h) 25 Oct 0130 25 Oct 0300 1.50 0.06
Problem stabbing sinker bars (will take 0.5 h) 25 Oct 0300 25 Oct 0330 0.50 0.02
RIH and recover Core 2R (will take 1.25 h); Core 336-U1383C-2R on deck at 0430 h, 20 Oct 25 Oct 0330 25 Oct 0430 1.00 0.04
Move bit from 70 to 76.6 mbsf (will take 0 h) 25 Oct 0430 25 Oct 0430 0.00 0.00
RCB core basement: 76.6–86.2 mbsf at 2.1 m/h; Core 336-U1383C-3R on deck at 1030 h 25 Oct 0430 25 Oct 1030 6.00 0.25
RCB core basement: 86.2–95.8 mbsf at 2.2 m/h; Core 336-U1383C-4R on deck at 1635 h 25 Oct 1030 25 Oct 1630 6.00 0.25
RCB core sediment: 95.8–105.4 mbsf at 2.2 m/h; Core 336-U1383C-5R on deck at 2230 h 25 Oct 1630 25 Oct 2230 6.00 0.25
RCB core basement: 105.4–115 mbsf at 2.2 m/h; Core 336-U1383C-6R on deck at 0310 h, 26 Oct 25 Oct 2230 26 Oct 0315 4.75 0.20
RCB core basement: 115–124.6 mbsf at 2.8 m/h; Core 336-U1383C-7R on deck at 0650 h 26 Oct 0315 26 Oct 0645 3.50 0.15
RCB core basement: 124.6–134.2 mbsf at 2.8 m/h; Core 336-U1383C-8R on deck at 1210 h 26 Oct 0645 26 Oct 1215 5.50 0.23
RCB core basement: 134.2–143.8 mbsf at 2.8 m/h; Core 336-U1383C-9R on deck at 1710 h 26 Oct 1215 26 Oct 1715 5.00 0.21
RCB core basement: 143.8–153.4 mbsf at 2.8 m/h; Core 336-U1383C-10R on deck at 2330 h 26 Oct 1715 26 Oct 2330 6.25 0.26
RCB core basement: 153.4–163.1 mbsf at 2.8 m/h; Core 336-U1383C-11R on deck at 0240 h, 27 Oct 26 Oct 2330 27 Oct 0245 3.25 0.14
RCB core basement: 163.1–172.7 mbsf at 2.8 m/h; Core 336-U1383C-12R on deck at 0610 h 27 Oct 0245 27 Oct 0615 3.50 0.15
RCB core basement: 172.7–182.3 mbsf at 2.8 m/h; Core 336-U1383C-13R on deck at 0950 h 27 Oct 0615 27 Oct 0945 3.50 0.15
RCB core basement: 182.3–191.9 mbsf at 4 m/h; Core 336-U1383C-14R on deck at 1335 h 27 Oct 0945 27 Oct 1330 3.75 0.16
RCB core basement: 191.9–192.8 mbsf at 4 m/h; Core 336-U1383C-15R on deck at 1605 h 27 Oct 1330 27 Oct 1600 2.50 0.10
Wiper trip: 192.8 mbsf to 60 mbsf and back 27 Oct 1600 27 Oct 2130 5.50 0.23
Deploy RCB core barrel and circulate mud sweep on bottom (will take 1 h) 27 Oct 2130 27 Oct 2230 1.00 0.04
RCB core basement: 192.8–201.4 mbsf at 3 m/h; Core 336-U1383C-16R on deck at 0605 h, 28 Oct 27 Oct 2230 28 Oct 0300 4.50 0.19
RCB core basement: 201.4–211.1 mbsf at 3 m/h; Core 336-U1383C-17R on deck at 0710 h 28 Oct 0300 28 Oct 0715 4.25 0.18
RCB core basement: 211.1–211.6 mbsf at 3 m/h; Core 336-U1383C-18R on deck at 0920 h 28 Oct 0715 28 Oct 0915 2.00 0.08
Circulation (will take 1 h) 28 Oct 0915 28 Oct 0945 0.50 0.02
Trip with top drive from 211.6 to 60 mbsf at 4 stands/h 28 Oct 0945 28 Oct 1000 0.25 0.01
Set back top drive (will take 0.5 h) 28 Oct 1000 28 Oct 1030 0.50 0.02
Clear seafloor at 1052 h            
Trip: depth to surface: from 60 mbsf to surface, ±1.5 h in 4425 m of water 28 Oct 1030 28 Oct 1630 6.00 0.25
Handle BHA (will take 1 h) 28 Oct 1630 28 Oct 1715 0.75 0.03
Bit clears rotary table at 1720 h            
Hole U1383C: RCB coring, Bit 2
Penetration rate taken from DSDP rates in 1976 for similar depths with RCB            
Inspect bit/float valve/support bearing and make up new RCB bit (will take 1 h) 28 Oct 1715 28 Oct 1815 1.00 0.04
Rig service/maintenance (will take 1 h) 28 Oct 1815 28 Oct 1915 1.00 0.04
Remove and repair hydraulic actuator assembly (air leak) (will take 8 h) 28 Oct 1915 29 Oct 0315 8.00 0.33
Make up new RCB bit assembly, space out core barrels, and pick up 3 drill collars; make up BHA (will take 2.25 h) 29 Oct 0315 29 Oct 0530 2.25 0.09
Reinstall repaired hydraulic actuator cylinder (will take 1 h) 29 Oct 0530 29 Oct 0630 1.00 0.04
Deploy camera (will take 0.5 h) 29 Oct 0630 29 Oct 0700 0.50 0.02
Trip: surface to mudline, ±1 h in 4425 m of water 29 Oct 0700 29 Oct 1230 5.50 0.23
Maneuver ship for reentry (will take 0.5 h); reenter at 1231 h 29 Oct 1230 29 Oct 1230 0.00 0.00
Trip: mudline to depth: from 0 to 60 mbsf, plus 0 h 29 Oct 1230 29 Oct 1330 1.00 0.04
Recover camera (will take 0.5 h) 29 Oct 1330 29 Oct 1415 0.75 0.03
Pick up top drive and space out drill pipe (will take 1 h) 29 Oct 1415 29 Oct 1515 1.00 0.04
Trip with top drive from 60 to 211.6 mbsf at 4 stands/h 29 Oct 1515 29 Oct 1715 2.00 0.08
Circulation (will take 1.25 h) 29 Oct 1715 29 Oct 1830 1.25 0.05
Deploy RCB core barrel and record SCRs (will take 0.75 h) 29 Oct 1830 29 Oct 1900 0.50 0.02
Core with 30 ft knobbies because of water depth, sea state, and slow ROP            
RCB core basement: 211.6–219.2 mbsf at 3 m/h; Core 336-U1383C-19R on deck at 2330 h 29 Oct 1900 29 Oct 2330 4.50 0.19
RCB core basement: 219.2–228.5 mbsf at 2.75 m/h; Core 336-U1383C-20R on deck at 0425 h, 30 Oct 29 Oct 2330 30 Oct 0430 5.00 0.21
RCB core basement: 228.5–237.7 mbsf at 2.75 m/h; Core 336-U1383C-21R on deck at 0800 h 30 Oct 0430 30 Oct 0800 3.50 0.15
RCB core basement: 237.7–247 mbsf at 2.75 m/h; Core 336-U1383C-22R on deck at 1130 h 30 Oct 0800 30 Oct 1130 3.50 0.15
RCB core basement: 247–256.2 mbsf at 2.75 m/h; Core 336-U1383C-23R on deck at 1915 h 30 Oct 1130 30 Oct 1615 4.75 0.20
Remove three knobbies, replace with drill pipe (will take 2 h) 30 Oct 1615 30 Oct 1815 2.00 0.08
Work pipe on bottom of hole/make connection/deploy core barrel (will take 1 h) 30 Oct 1815 30 Oct 1845 0.50 0.02
RCB core basement: 256.2–266.2 mbsf at 2.75 m/h; Core 336-U1383C-24R on deck at 2330 h 30 Oct 1845 30 Oct 2330 4.75 0.20
RCB core basement: 266.2–275.4 mbsf at 5.5 m/h; Core 336-U1383C-25R on deck at 0245 h, 31 Oct 30 Oct 2330 31 Oct 0245 3.25 0.14
RCB core basement: 275.4–284.7 mbsf at 3.5 m/h; Core 336-U1383C-26R on deck at 0645 h 31 Oct 0245 31 Oct 0645 4.00 0.17
RCB core basement: 284.7–294 mbsf at 2.75 m/h; Core 336-U1383C-27R on deck at 1135 h 31 Oct 0645 31 Oct 1130 4.75 0.20
RCB core basement: 294–299.2 mbsf at 1.3 m/h; Core 336-U1383C-28R on deck at 1630 h 31 Oct 1130 31 Oct 1630 5.00 0.21
RCB core basement: 299.2–303.7 mbsf at 2.5 m/h; Core 336-U1383C-29R on deck at 2005 h 31 Oct 1630 31 Oct 2000 3.50 0.15
RCB core basement: 303.7–312.1 mbsf at 1.9 m/h; Core 336-U1383C-30R on deck at 0230 h, 1 Nov 31 Oct 2000 1 Nov 0230 6.50 0.27
RCB core basement: 312.1–321.7 mbsf at 2 m/h; Core 336-U1373C-31R on deck at 0845 h 1 Nov 0230 1 Nov 0845 6.25 0.26
RCB core basement: 321.7–331.5 mbsf at 2.75 m/h; Core 336-U1383C-32R on deck at 1355 h 1 Nov 0845 1 Nov 1400 5.25 0.22
Circulation (will take 1 h) 1 Nov 1400 1 Nov 1400 0.00 0.00
Pump 30 bbl while cutting last meter of core            
Wiper trip 1: 331.5–60 mbsf and back; numerous ledges and tight spots required reaming with top drive plus circulation; 4 m of fill on bottom; 70 bbl high-vis mud sweep 1 Nov 1400 2 Nov 0130 11.50 0.48
Circulation (will take 0.75 h) 2 Nov 0130 2 Nov 0215 0.75 0.03
Wiper trip 2: 331.5–60 mbsf and back; pull to casing shoe (no problems); RIH using motion compensator but no top drive; no hang-ups and no fill on bottom 2 Nov 0215 2 Nov 0430 2.25 0.09
Circulation (will take 0 h) 2 Nov 0430 2 Nov 0430 0.00 0.00
Wiper trip 3: 331.5–80 mbsf and back; same result as wiper trip 2 2 Nov 0430 2 Nov 0545 1.25 0.05
Circulation (will take 0 h) 2 Nov 0545 2 Nov 0545 0.00 0.00
Trip: depth to surface: from 331.5 mbsf to surface, ±1 h in 4425 m of water 2 Nov 0545 2 Nov 1245 7.00 0.29
Clear seafloor at 0625 h            
Handle BHA (will take 1 h) 2 Nov 1245 2 Nov 1315 0.50 0.02
Bit clears rotary table at 1315 h            
Hole U1383C: downhole logging, hydrologic packer experiments, and depth check
Make up stand of 6.75 inch drill collars for CORK (will take 1 h) 2 Nov 1315 2 Nov 1530 2.25 0.09
Handle BHA (will take 2 h) 2 Nov 1530 2 Nov 1645 1.25 0.05
Deploy camera (will take 0.5 h) 2 Nov 1645 2 Nov 1715 0.50 0.02
Trip: surface to mudline, ±1 h in 4425 m of water 2 Nov 1715 2 Nov 2345 6.50 0.27
Maneuver ship for reentry (will take 0 h); reenter at 2342 h (3 min reentry) 2 Nov 2345 2 Nov 2345 0.00 0.00
Trip: mudline to depth: from 0 to 55 mbsf, plus 0.25 h 2 Nov 2345 3 Nov 0000 0.25 0.01
Rig up (will take 1 h) 3 Nov 0000 3 Nov 0100 1.00 0.04
Triple combination: log from 55 to 331.5 mbsf at 275 m/h 3 Nov 0100 3 Nov 1245 11.75 0.49
FMS-sonic: log from 55 to 331.5 mbsf at 275 m/h 3 Nov 1245 3 Nov 2245 10.00 0.42
Rig down (will take 1 h) 3 Nov 2245 3 Nov 2315 0.50 0.02
Pick up top drive and space out drill pipe (will take 0.75 h) 3 Nov 2315 4 Nov 0015 1.00 0.04
Packer testing: based on 2 injection tests per packer seat, reduced time allocated from 36 to 26 h            
Packer: from 60 to 290 mbsf doing 3 tests (will take 11 h) 4 Nov 0015 4 Nov 1100 10.75 0.45
Packer Set 1 inside casing; 3 failed attempts (using up to 2200 psi); heave too high; packer slipping or deflating            
Packer Set 2 in open hole at ~141 mbsf            
Packer Set 3 in open hole at ~196 mbsf; couldn't get packer to seat; test canceled            
Set back top drive (will take 0.5 h) 4 Nov 1100 4 Nov 1130 0.50 0.02
RIH for depth check (will take 0.5 h) 4 Nov 1130 4 Nov 1200 0.50 0.02
Move bit from 55 to 331.5 mbsf (will take 0 h) 4 Nov 1200 4 Nov 1200 0.00 0.00
Handle camera (will take 0.5 h) 4 Nov 1200 4 Nov 1215 0.25 0.01
Trip: depth to mudline: from 331.5 mbsf to mudline, plus 0 h 4 Nov 1215 4 Nov 1315 1.00 0.04
Clear seafloor at 1310 h            
Hole U1383B: free-fall deployment of ROV platform; drill pipe vessel over to Hole U1383B 4 Nov 1315 4 Nov 1330 0.25 0.01
Maneuver ship for reentry (will take 0.5 h); reenter at 1350 h 4 Nov 1330 4 Nov 1345 0.25 0.01
Recover camera from seafloor 4 Nov 1345 4 Nov 1515 1.50 0.06
Make up and drop ROV platform from surface (will take 2 h) 4 Nov 1515 4 Nov 1645 1.50 0.06
Deploy camera to seafloor 4 Nov 1645 4 Nov 1815 1.50 0.06
Observe ROV platform in reentry cone/pull clear of seafloor/prepare for slip and cut (will take 0.25 h) 4 Nov 1815 4 Nov 1830 0.25 0.01
Clear seafloor at 1818 h            
Slip/cut drill line (will take 1.5 h) 4 Nov 1830 4 Nov 2015 1.75 0.07
Recover camera during slip and cut            
Rig up CORK umbilicals in moonpool while POOH with drill string         0.00 0.00
Trip: depth to surface: from (mudline) 0 mbsf to surface, ±1 h in 4425 m of water 4 Nov 2015 5 Nov 0200 5.75 0.24
Handle BHA (will take 1 h) 5 Nov 0200 5 Nov 0300 1.00 0.04
Hole U1383C: assemble/install CORK and OsmoSampler string
Make up CORK plumb bob with ten 15 ft long, 6.75 inch drill collars (will take 2 h) 5 Nov 0300 5 Nov 0500 2.00 0.08
Rig up for casing (will take 1 h) 5 Nov 0500 5 Nov 0600 1.00 0.04
Install crossovers, 5.5 inch casing pup, landing seat, and packer (will take 2 h) 5 Nov 0600 5 Nov 0800 2.00 0.08
Make up packer connections (will take 1 h) 5 Nov 0800 5 Nov 0845 0.75 0.03
Run 38.2 m of 4.5 inch fiberglass casing (will take 2 h) 5 Nov 0845 5 Nov 1015 1.50 0.06
Install second packer and make up hydraulic connections at both ends (will take 2 h) 5 Nov 1015 5 Nov 1215 2.00 0.08
Install 80 m of 4.5 inch fiberglass casing per plan (will take 2 h) 5 Nov 1215 5 Nov 1415 2.00 0.08
Install third packer and make up hydraulic connections (will take 2 h) 5 Nov 1415 5 Nov 1630 2.25 0.09
Install 48 m of 4.5 inch steel casing (will take 2 h) 5 Nov 1630 5 Nov 1715 0.75 0.03
Make up final umbilical terminations to CORK head (will take 2 h) 5 Nov 1715 5 Nov 1915 2.00 0.08
Hang-off CORK head on moonpool C-plates and remove CORK running tool (will take 1 h) 5 Nov 1915 5 Nov 1945 0.50 0.02
Make up and deploy instrument string (will take 1.5 h) 5 Nov 1945 5 Nov 2115 1.50 0.06
Make up CORK running tool and rig-up packer inflate line (will take 0.5 h) 5 Nov 2115 5 Nov 2145 0.50 0.02
Replace bushings. Pick up one stand of drill collars and lower CORK head below keel to equalize pressure. Raise head back to moonpool 5 Nov 2145 5 Nov 2230 0.75 0.03
Install OsmoSampler pump and close all valves (will take 0.75 h) 5 Nov 2230 5 Nov 2315 0.75 0.03
Remove moonpool grating and test-fit camera frame over CORK head (will take 0.75 h) 5 Nov 2315 6 Nov 0000 0.75 0.03
Handle BHA (will take 0.5 h) 6 Nov 0000 6 Nov 0030 0.50 0.02
Deploy camera (will take 0.5 h) 6 Nov 0030 6 Nov 0100 0.50 0.02
Trip: surface to mudline, plus 2 h in 4425 m of water 6 Nov 0100 6 Nov 0915 8.25 0.34
Maneuver ship for reentry (will take 0.5 h); reenter at 0941 h 6 Nov 0915 6 Nov 0945 0.50 0.02
RIH slowly, pick up top drive, space out and land CORK (will take 1.75 h); CORK lands at 1127 h 6 Nov 0945 6 Nov 1130 1.75 0.07
Recover camera frame and pressure up drill string to inflate CORK packers (will take 2.25 h) 6 Nov 1130 6 Nov 1315 1.75 0.07
Assemble ROV platform and make up with deployment tool and camera frame (will take 1.25 h) 6 Nov 1315 6 Nov 1415 1.00 0.04
Deploy camera with ROV platform (will take 3 h) 6 Nov 1415 6 Nov 1630 2.25 0.09
Monitor ROV release (will take 0.25 h) 6 Nov 1630 6 Nov 1645 0.25 0.01
Recover camera from seafloor 6 Nov 1645 6 Nov 1800 1.25 0.05
Remove slings from camera at surface            
Remove ROV deployment slings and assembly (will take 0.5 h) 6 Nov 1800 6 Nov 1830 0.50 0.02
Deploy camera to seafloor 6 Nov 1830 6 Nov 2015 1.75 0.07
Release CORK (will take 0.25 h) 6 Nov 2015 6 Nov 2015 0.00 0.00
Survey CORK (will take 0.25 h) 6 Nov 2015 6 Nov 2015 0.00 0.00
Set back top drive (will take 0.5 h) 6 Nov 2015 6 Nov 2045 0.50 0.02
Trip: mudline to surface, ±1.5 h in 4425 m of water 6 Nov 2045 7 Nov 0300 6.25 0.26
Recover camera (will take 0.25 h) 7 Nov 0300 7 Nov 0245 –0.25 –0.01
Set back BHA and lay out CORK running tool (will take 0.25 h) 7 Nov 0245 7 Nov 0315 0.50 0.02
Hole U1383C totals: 19 Oct 1745 7 Nov 0315 441.50 18.40

Times are given as local ship time, which is Universal Time Coordinated (UTC) – 3 h for all on-site operations. BHA = bottom-hole assembly. SCR = slow circulation rate. spm = strokes per minute, ROP = rate of penetration. POOH = pull out of hole, RIH = run in hole. TD = total depth. DSDP = Deep Sea Drilling Project. FMS = Formation MicroScanner.