GEOPHYSICS

The EPSP approved the sites proposed and, as requested, approved a range of shotpoints where each site could be positioned to improve the ice contingency plans. The EPSP determined that it would not be necessary to acquire any additional cross-lines before drilling, and approved a 200 meter wide swath along the approved shot point intervals (Table T1). Further seismic lines will not therefore be collected for site-selection purposes. However, seismic equipment and an operational team will be on board Oden, and additional could be acquired for scientific purposes after the successful completion of sites.