Table T1. Operations summary and time estimates for Expedition 304.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Ponta Delgada, Azores
|
Sea voyage from Ponta Delgada to Site AMFW-01A, 936 nmi @ 10.5 kt
|
3.7
|
|
|
AMFW-01A
|
30.170°N,
42.123°W
|
1630
|
Hole A: Bare rock spud, RCB 4.5 m cores 0130 mbsf
|
|
3.1
|
|
|
|
Drop bit, log: triple combo, FMS/sonic, UBI
|
|
|
1.2
|
|
|
|
Hole B: HRRS hammer drill-in 22 m of 133/8 inch casing
|
|
1.9
|
|
|
|
|
Underream 143/4 inch hole with bicenter bit to ~130 mbsf
|
|
3.1
|
|
|
|
|
Run 120 m of 103/4 inch casing with MM and underreamer
|
|
1.7
|
|
|
|
|
Set retainer, cement 103/4inch casing Subtotal = 11.9 days
|
|
0.9
|
|
|
|
Transit from Site AMFW-01A to Site AMHW-01A, 3.3 nmi @ 1.0 kt
|
0.1
|
|
|
AMHW-01A
|
30.192°N,
42.065°W
|
2580
|
Hole A: HRRS hammer drill-in 22 m of 133/8 inch casing
|
|
2.1
|
|
|
|
RCB 4.5 m cores 2270 mbsf; ADCB 4.5 m cores 70130 mbsf
|
|
4.4
|
|
|
|
Underream 143/4 inch hole with bicenter bit to ~130 mbsf
|
|
3.2
|
|
|
|
Run 120 m of 103/4 inch casing with MM and underreamer
|
|
1.8
|
|
|
|
|
Set retainer, cement 103/4 inch casing
|
|
0.9
|
|
|
|
|
Clean out cement, RCB 4.5 m cores 130250 mbsf
|
|
4.7
|
|
|
|
|
RCB 4.5 m cores 250370 mbsf
|
|
4.5
|
|
|
|
|
RCB 4.5 m cores 370500 mbsf
|
|
4.2
|
|
|
|
|
Drop bit; log: triple combo, FMS/sonic, UBI Subtotal = 27.6 days
|
|
|
1.8
|
Ponta Delgada, Azores
|
Sea voyage from Site AMHW-01A to Ponta Delgada, 932 nmi @ 10.5 kt
|
3.7
|
|
|
|
|
|
|
7.5
|
36.5
|
3.0
|
|
|
|
|
|
|
If first footwall pilot hole fails (not peridotite/gabbro or bad hole conditions), attempt another pilot hole.
|
|
|
|
Footwall
peridotite
|
~30.17°N,
~42.12°W
|
~1630
|
Bare rock spud, RCB 4.5 m cores 0130 mbsf
|
|
3.1
|
|
|
Drop bit; log: triple combo, FMS/sonic, UBI Subtotal = 4.3 days
|
|
|
1.2
|
If first footwall pilot hole OK but HRRS fails, attempt second HRRS installation and core (leave time for hanging wall site [27.6 days]).
|
Footwall
peridotite
|
~30.17°N,
~42.12°W
|
~1630
|
HRRS hammer drill-in 22 m of 133/8 inch casing
|
|
1.9
|
|
|
Underream 143/4 inch hole with bicenter bit to ~130 mbsf
|
|
3.1
|
|
|
|
|
Run 120 m of 103/4 inch casing with MM and underreamer
|
|
1.7
|
|
|
|
|
Set retainer, cement 103/4 inch casing Subtotal = 7.6 days
|
|
0.9
|
|
If first footwall pilot hole and HRRS OK but first hanging wall HRRS fails (insufficient time to deploy second hanging wall HRRS),
|
|
deepen footwall hole as time permits (no more than 1820 days).
|
|
|
|
Footwall
peridotite
|
~30.17°N,
~42.12°W
|
~1630
|
Clean out cement, RCB 4.5 m cores 130250 mbsf
|
|
4.2
|
|
|
RCB 4.5 m cores 250370 mbsf Subtotal = 8.3 days
|
|
4.1
|
|
|
|
|
RCB 4.5 m cores 370490 mbsf Subtotal = 12.1 days
|
|
3.8
|
|
|
|
|
RCB 4.5 m cores 490610 mbsf Subtotal = 16.4 days
|
|
4.3
|
|
|
|
|
RCB 4.5 m cores 610730 mbsf Subtotal = 20.8 days
|
|
4.4
|
|
Transect of shallow MDCB core holes in footwall.
|
|
Footwall
peridotite
|
~30.17°N,
~42.12°W
|
~1630
|
Trip in/out with XCB/MDCB BHA
|
|
0.6
|
|
|
MDCB core two holes 0 to ~9.0 mbsf average Subtotal = 1.3 days
|
|
0.7
|
|
Bare rock spud and RCB 4.5 m cores to bit destruction in footwall.
|
|
|
|
Footwall
peridotite
|
~30.17°N,
~42.12°W
|
~1630
|
RCB 4.5 m cores to bit destruction 0 to ~150 mbsf
|
|
3.9
|
|
|
Drop bit; log: triple combo, FMS/sonic, UBI Subtotal = 5.5 days
|
|
|
1.6
|
Shallow cores to recover upper part of footwall (detachment surface).
|
|
|
|
Footwall
peridotite
|
~30.17°N,
~42.12°W
|
~1630
|
RCB 4.5 m cores 0 to ~26 mbsf
|
|
1.6
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: RCB = rotary core barrel, FMS = Formation MicroScanner, UBI = ultrasonic borehole imager, HRRS = hard rock reentry system, MM = mud motor, ADCB = advanced diamond core barrel, XCB = extended core barrel, MDCB = motor-driven core barrel, BHA = bottom-hole assembly.