Table T2. Stage 1 measurement-while-drilling operations summary for primary sites.

Proposed
site
Water depth (m)
MWD depth (mbsf)
Operational time (days)
Total time (days)
BT4-2A
1476
340
1.2
1.2
BT4-4A
1435
230
1.0
1.0
Transit 2

2.0
URS-3C
1321
238
1.0
1.0
URS-2C
1262
358
1.2
1.2
URS-1B
1057
612
1.9
1.9
Total:
8.3

Notes: MWD = measurement while drilling. The time estimates include rig-up through rig-down and stow.