Table T1. Operation plan and time estimate for Expedition 314.

Proposed site Location Depth
(mbsf)
Operations description Days
Latitude Longitude Transit LWD

Shingu port

Science party boards ship
2.0 (in port)
NT2-03B, NT1-03A


Start of Expedition 314 with pilot hole drilling
0.4
7.1
NT1-01A 32°44.8878′N 136°55.0236′E 3610 Transit ~18 nmi to proposed Site NT1-01A at 6 ktHole A: LWD/MWD to 600 mbsf
0.13
3.4
NT2-03B 33°14.300′N 136°42.650′E 2178 Transit ~32 nmi to proposed Site NT2-03B at 6 ktHole A: LWD/MWD to 1000 mbsf
0.22
3.28
NT3-01B 33°18.020′N 136°38.180′E 1966 Transit ~6 nmi to proposed Site NT3-01B at 6 ktHole A: LWD/MWD to 1400 mbsf with 9-5/8 inch casing ~1000 m
0.04
14.46
NT2-01B 33°13.320′N 136°42.200′E 2391 Transit ~6 nmi to proposed Site NT2-01B at 6 ktHole A: LWD/MWD to 1000 mbsf
0.04
3.46
NT1-03B 33°01.635′N 136°47.639′E 3832 Transit ~13 nmi to proposed Site NT1-03B at 6 ktHole A: LWD/MWD to 950 mbsf
0.10
3.4
NT1-07A 32°49.730′N 136°52.890′E 4062 Transit ~13 nmi to proposed Site NT1-07A at 6 ktHole A: LWD/MWD to 1200 mbsf
0.10
4.9

Ugata, Shima

Helicopter transfer to Ugata, Shima in Mie PrefectureEnd of Expedition 314





Contingency:
15




Total operating days:
57

Note: LWD = logging while drilling, MWD = measurement while drilling.

Close  |   Top of page