Table T1. Operations plan and time estimate for proposed Site NT2-03, Expedition 315.

Hole PTD
(mbsf)
Water depth (m) Total (mbsl) Operations Estimated days Number of cores







B 600 2178 2778 Prepare for drilling (guidehorn, BHA, etc.)
1.0





RIH HPCS/ESCS assembly
0.5





Core with HPCS and ESCS to 600 m
5.5
64




Carry out jet-in test before coring and start coring at new hole
- Try to take core by HPCS and ESCS to PTD; if PTD cannot be reached, go to Hole C
- Require core orientation- Hole size: 11-7/16 inch
- Temperature measurement every 50 m by APCT-3 or DVTP






POOH, lay out HPCS/ESCS assembly
0.5





Total drilling days:
7.5

Hole B remarks:- No retrieving guidehorn
- Penetration rate 120 m/day
- HPCS/ESCS 9.5 m/bbl
- Pump weighted mud into hole before POOH (abandonment)
- May encounter thousands of faults and deformed sequences









C 1000 2178 3428 Move to Hole C, RIH RCB assembly
0.5





Drill to 600 m by RCB
1.5





If Hole B cannot reach PTD, start to take core from refusal depth of Hole B
- Limit daily progress to 400 m/day to maintain good hole
- Hole size: 9-7/8 inch
- Core with RCB to 1000 m
6.5
69




Take 650 m core by RCB
- Take overlapping core of Hole B
- Wiper trip
0.5





Displace with weighted mud, drop bit, POOH to seafloor
0.5





POOH, lay out RCB assembly
0.5





Retrieve guidehorn
0.5





Total drilling days:
10.5

Hole C remarks:
- RCB 9.5 m/bbl
- If core does not go to 700 m, consider coring at riser hole






Expedition 315 total drilling days:
18.0





Transit between base and location:
0.0





Equipment and fuel supply before expedition:
0.0





Total operation days (without contingency):
18.0





Contingency:
4.0





Expedition 315 total operation days:
22.0








Riser 700 2178 2878 Prepare for running BHA and 36 inch conductor
0.5





Run and jet-in 36 inch conductor to 60 m
- Conductor setting depth will be decided by result of jet-in test
1.5





Drill 26 inch hole to 700 m
- Set guidehorn
2.0





Run and cement 20 inch casing
3.0





POOH, lay out BHA
1.0





Total drilling days:
8.0

Riser hole remarks:
- No retrieving guidehorn






Expedition 315 riser total drilling days:
8.0





Transit between base and location:
0.0





Equipment and fuel supply before expedition:
0.0





Total operation days (without contingency):
8.0





Contingency:
5.0





Expedition 315 riser total operation days:
13.0








Notes: PTD = proposed total depth, BHA = bottom-hole assembly, RIH = run in hole, HPCS = hydraulic piston coring system, ESCS = extension shoe coring system, POOH = pull out of hole, DVTP = Davis-Villinger Temperature Probe, APCT-3 = third-generation advanced piston corer temperature tool, RCB = rotary core barrel