Table T2. Summary of operations for Pacific equatorial Expedition 321.
Site Location
(latitude, longitude)
Seafloor
depth
(mbrf)
Operations description Duration (days)
Task Transit Drilling/Coring Logging
Honolulu, Hawaii
Begin expedition
5.00



Transit ~1128 nmi to Site PEAT-2C at 10.5 kt

4.4

PEAT-2C
EPSP approved
to 250 mbsf
11°54.711′N,
141°02.744′W
4952

Hole A: APC ~70 m/XCB to ~163 mbsf (~1 m into basement)
- 3 APCT-3 and 2 DVTP temperature measurements
- Wireline logging with triple combo and FMS-sonic


2.2
1.0
Hole B: APC ~70 m/XCB to ~162 mbsf


1.8

Subtotal days on site:
3.2

Transit ~961 nmi to Site PEAT-6C at 10.5 kt

3.8

PEAT-6C
EPSP approved
to 400 mbsf
05°18.736′N,
126°16.997′W
4362


Hole A: APC ~70 m/XCB to ~363 mbsf (~1 m into basement)
- 3 APCT-3 and 2 DVTP temperature measurements
- Wireline logging with triple combo and FMS-sonic
- VSP with VSI


3.5
1.5
Hole B: APC ~70 m/XCB to ~362 mbsf


2.9

Hole C: APC ~70 m/XCB to ~362 mbsf


3.3

Subtotal days on site:
11.2

Transit ~204 nmi to Site PEAT-7C at 10.5 kt

0.8

PEAT-7C
EPSP approved
to 480 mbsf
03°50.009′N,
123°12.352′W
4502


Hole A: APC ~70 m/XCB to ~453 mbsf (~1 m into basement)
- 3 APCT-3 and 2 DVTP temperature measurements
- Wireline logging with triple combo and FMS-sonic


4.2
1.1
Hole B: APC ~70 m/XCB to ~452 mbsf


3.6

Hole C: APC ~70 m/XCB to ~452 mbsf


3.9

Subtotal days on site:
12.8

Transit ~1726 nmi to San Diego, California, at 10.5 kt

6.8

San Diego, California
Discharge science party
2.0



Juan de Fuca remedial cementing*


Transit ~1134 nmi to Hole U1301B at 10.5 kt

4.5

Hole U1301B 47.7538°N,
127.7638°W
2667
Install DP stabilizing collar for cementing operations; reenter hole (1.1 days)
Pump additional cement into reentry hole/POOH (0.4 days)


1.5

Subtotal days on site:
1.5



DP offset ~36 m (0.7 nmi) to Hole U1301A at 0.5 kt

0.0

Hole U1301A 47.7535°N,
127.7639°W
2671
Reenter Hole U1301A after offsetting from Hole U1301B (0.6 days)
Pump additional cement into reentry hole/POOH (0.5 days)
Recover drill string/continue to ensure all holes plugged with cement (1.4 days)


2.5

Subtotal days on site:
2.5



Transit ~187 nmi to Astoria, Oregon, at 10.5 kt

0.7

Astoria, Oregon
End expedition

21.0
29.4
3.6

Subtotal time on site:
33.0

Total operating days:
54.0

Total expedition (including 7 port call days):
61.0

Notes: Seafloor depth = prospectus water depth plus 11.0 m adjustment from water line to rig floor (i.e., drillers depth). * = Details on the Juan de Fuca remedial cementing operations can be found at iodp.tamu.edu/scienceops/expeditions/juan_de_fuca.html. All costs associated with the Juan de Fuca "remedial cementing" program will be calculated in a separate IPE and are not included in this Pacific equatorial 2 IPE. The Juan de Fuca program is included in the operating plan only because it impacts operations. APC = advanced piston corer, XCB = extended core barrel, APCT-3 = advanced piston corer temperature-3 tool, DVTP = Davis-Villinger Temperature Probe, triple combo = triple combination, FMS-sonic = Formation MicroScanner-sonic tool string, VSP = vertical seismic profile, VSI = Vertical Seismic Imager, DP = dynamic positioning, POOH = pull out of hole.