Table T1. Planned drill site details.
Hole Latitude,
Longitude
Seafloor
depth
Operations description Transit
(days)
Drilling/
Coring
(days)
Logging
(days)
San Diego, California Begin Expedition 1 day port call



Transit ~1134 nmi to Hole U1301B @ 9.0 kt
5.3

U1301B 47.7538°N,
127.7638°W
2667 Hole U1301B
- Lower end of pipe to/into reentry cone and pump cement into
reentry cone
- Flush drill pipe and offset to Hole 1301A

2.5






U1301A 47.7535°N,
127.7639°W

2671 Hole U1301A
- Lower end of pipe to/into reentry cone and pump cement into
reentry cone
- Flush drill pipe and inspect cement job at both holes; recover
drill string

2.5



     



Subtotal days onsite:
5.0





Transit ~181 nmi to Victoria, B.C. Canada @ 10.5 kt
0.7

Victoria, B.C., Canada End Expedition 6.0 5.0 0.0
 
Subtotal onsite time:
5.0  
Total operating days:
11.0
Total Expedition (including 1 port call day):
12.0


Notes: Seafloor depth is prospectus water depth plus 11.0 m adjustment from water line to rig floor (i.e., drillers depth). San Diego port call is assumed to be 1.0 day. Cementing includes ~24 h of contingency time split evenly between the two holes. Transit speed from San Diego to Hole U1301B is assumed to be 9.0 kt due to opposing current. All other transits assume 10.5 kt.