Table T1. Operations plan.
Site Location
(latitude,
longitude)
Seafloor
depth
(mbsf)
Operations description Duration (days)
Task Transit Drilling/
Coring
Logging
Yokohama, Japan
 



Transit 1115 nmi to Site SRNH-2 @ 10.5 kt   4.4

SRNH-2 38°04.400'N
162°38.710'E
3654 Locate site, measure tubulars, and trip drill string to mudline
 
0.4
Drill to 144 mbsf
 
0.2
RCB from 144 mbsf to 194 mbsf in sediment
 
0.5
Wiper trip and flush hole with mud
 


RCB from 194 mbsf to 294 mbsf (100 m into bsmt)
 
2.0
Wiper trip and displace hole with mud
 


Release bit w/MBR and set end of pipe at 80 mbsf
 
0.5
Log hole with triple combo and FMS-sonic
 

0.8
Recover drill string and secure drilling equipment
 
0.4
Subtotal days on site: 4.8

Transit 232 nmi from Site SRNH-2 to SRCH-5 @ 10.5 kt   0.9

SRCH-5 36°06.944'N
158°27.526'E
3148 Locate site and trip drill string to mudline
 
0.4
Drill to 134 mbsf
 
0.2
RCB from 134 mbsf to 184 mbsf in sediment
 
0.4
Wiper trip and flush hole with mud
 


RCB from 184 mbsf to 384 mbsf (200 m into basement)
 
4.0
Wiper trip and displace hole with mud
 


Release bit w/MBR and set end of pipe at 80 mbsf
 
0.6
Log hole with triple combo and FMS-sonic
 

0.7
Recover drill string and secure drilling equipment
 
0.4
Subtotal days on site: 6.7

Transit 112 nmi from SRCH-5 to SRSH-6 @ 10.5 kt   0.4

SRSH-6 34°25.320'N
159°22.932'E
3285 Locate site and trip drill string to mudline
 
0.4
Drill to 127 mbsf
 
0.2
RCB from 127 mbsf to 177 mbsf in sediment
 
0.4
Wiper trip and flush hole with mud
 


RCB from 177 mbsf to 277 mbsf (100 m into basement)
 
2.1
Wiper trip and displace hole with mud
 


Release bit w/MBR and set end of pipe at 80 mbsf
 
0.4
Log hole with triple combo and FMS-sonic
 

0.7
Recover drill string and secure drilling equipment
 
0.3
Subtotal days on site: 4.5

Transit 115 nmi from SRSH-6 to SRSH-3B @ 10.5 kt   0.5

SRSH-3B 32°30.474'N
159°14.082'E
3477 Locate site and trip drill string to mudline
 
0.4
Drill to 119 mbsf into sediment
 
0.2
RCB from 119 mbsf to 169 mbsf into sediment
 
0.4
Wiper trip and flush hole with mud
 


RCB from 169 mbsf to 308 mbsf (139 m into basement)
 
2.7
Wiper trip and flush hole with mud
 


Rig up/deploy Free Fall Funnel (FFF), inspect FFF w/VIT
 


Round trip drill for bit change and reenter FFF
 
1.2
RCB from 308 mbsf to 469 mbsf (161 m into basement)
 
3.7
Wiper trip and flush hole with mud
 


Displace hole with logging mud, drop bit with MBR
 


Set end of pipe at 80 mbsf
 
0.6
Log hole with triple combo, FMS-sonic, and UBI
 

1.3
Recover drill string and secure drilling equipment
 
0.4
Subtotal days on site: 10.9

Transit 145 nmi from SRSH-3B to SRSH-8 @ 10.5 kt   0.6

SRSH-8 31°05.752'N
156°55.981'E
4670 Locate site and trip drill string to mudline
 
0.4
Drill to 105 mbsf in sediment
 
0.2
RCB from 105 mbsf to 155 mbsf in sediment
 
0.5
Wiper trip and flush hole with mud
 


RCB from 155 mbsf to 255 mbsf (100 m into basement)
 
2.1
Wiper trip and displace hole with mud
 


Release bit w/MBR and set end of pipe at 80 mbsf
 
0.5
Log hole with triple combo and FMS-sonic
 

0.9
Recover drill string and secure drilling equipment for transit
 
0.5
Subtotal days on site: 5.1

Transit 3129 nmi to Townsville, Australia @ 10.5 kt   12.4

Townsville, Australia
  19.2 27.6 4.4
Subtotal time on site: 32.0
Contingency: 4.8
Total operating days: 56.0
Total expedition (including 5 port call days): 61.0