Site
|
Proposed total depth (mbsf) |
Water depth (m) |
Total (mbsf) |
Operation |
Estimated days |
Total days |
|
|
|
|
Loading at Shingu |
4.0 |
4.0 |
C0002
|
3300 |
1939 |
3300 |
Move to site, preparation for spud, deploy transponders |
5.0 |
9.0 |
Run and jet in 36 inch conductor to 60 mbsf
|
4.0 |
13.0 |
Set 20 inch casing:
• Drill 26 inch hole from 60 to 800 mbsf
• Run and cement 20 inch casing
• Set corrosion cap, retrieve transponders |
3.0
5.0
2.0 |
23.0 |
|
|
|
|
Move back to Shingu |
1.0 |
24.0 |
|
|
|
|
Total days: |
24.0 |