Table T1. Operations and time estimates for Expedition 326, riser Site C0002.

Site Proposed
total depth
(mbsf)
Water
depth
(m)
Total
(mbsf)
Operation Estimated
days
Total
days
        Loading at Shingu 4.0 4.0
C0002 3300 1939 3300 Move to site, preparation for spud, deploy transponders 5.0 9.0
Run and jet in 36 inch conductor to 60 mbsf 4.0 13.0
Set 20 inch casing:
• Drill 26 inch hole from 60 to 800 mbsf
• Run and cement 20 inch casing
• Set corrosion cap, retrieve transponders

3.0
5.0
2.0
     


23.0
        Move back to Shingu 1.0 24.0
        Total days: 24.0