Table T1. Expedition 338 operations and time estimates.

Operation Depth
(mbsf)
Days Subtotal
(d)
Total
(d)
Transit, deploy transponders, retrieve corrosion cap, preparation for spud 5.0 5.0 5.0
Run and set BOP and riser, test BOP 11.0 11.0 16.0
Set 16 inch casing        
DOC and LOT 850 2.0    
Drill RWD (LWD) to 2300 mbsf 2300 9.0    
Run and cement 16 inch casing 2300 6.0    
Test BOP 2.0 19.0 35.0
Set 13-3/8 inch casing        
DOC and LOT 2300 2.0    
Cut core from 2300 to 2400 mbsf 2400 4.0    
Underream (LWD) to 17 inch hole from 2300 to 3600 mbsf 3600 16.0    
Run and cement 13-3/8 inch casing to 3600 mbsf 3600 6.0    
Test BOP (2 times) 4.0 32.0 67.0
Suspend hole        
Set cement plug or bridge plug in hole 3.0    
Retrieve BOP and marine riser 9.0 12.0 79.0
Set corrosion cap, retrieve transponders 2.0 3.0 82.0
Transit to Shingu 1.0    
Contingency 20.0 20.0 102.0
Mechanical down time (operation time × 3%)        
Wait on weather (operation time × 1.5%)        
Typhoon evacuation (4 times × 4 days)        

Water depth = 1968 m. BOP = blowout preventer. DOC = drill out cement. LOT = leak-off test. RWD = reaming while drilling, LWD = logging while drilling.