Table T1. Expedition 352 primary sites and operations plan.

Site
Location (latitude, longitude)
Seafloor depth (mbrf)
Operations description
 
Transit (days)
Drilling, coring (days)
Logging (days)
Yokohama Begin expedition 5.0 port call days
 
Transit ~448 nmi to BON-2A at 10.5 kt
 
1.8
 
 
BON-2A
Total depth pending EPSP approval
28°24.46′N, 142°36.55′E 3148 Hole A - Depth check and jet-in test     0.8  
Hole B - APC/XCB core to basement at ~120 mbsf                  0.8              
Subtotal days on site: 1.6      
 
Transit ~8 nmi to BON-1A in DP mode at 1.5 kt
 
0.2
 
 
BON-1A
Total depth pending EPSP approval
28°27.01′N, 142°45.35′E 4789 Hole A - Depth check and jet-in test     0.6  
Hole B - APC/XCB core to basement at ~260 mbsf     2.5  
Hole C - Install reentry system to ~265 mbsf     7.6  
1. Deploy reentry cone and jet-in ~60 m 16” casing (to ~60 mbsf)        
2. Drill 14-3/4” diameter hole into sediment (~260 mbsf) then 10 m into basement        
3. Deploy 10-3/4” casing/land hanger in reentry cone, place shoe at ~265 mbsf        
4. Cement casing shoe/release casing hanger/flush pipe/POOH        
Hole C - RCB core from 270 to 1010 mbsf - 750 m into basement     15.3 1.3
1. RCB core basement from 270 to ~1010 mbsf        
2. Change bits as required        
3. Condition hole, drop bit on seafloor, and log with triple combo and FMS-sonic        
Subtotal days on site: 27.3      
 
Transit ~8 nm to BON-2A at 10.5 kt
 
0.1
 
 
BON-2A
Total depth pending EPSP approval
28°24.46′N, 142°36.55′E 3148 Hole C - Install reentry system to ~125 mbsf     6.4  
1. Deploy reentry cone and jet-in ~60 m 16” casing (to ~60 mbsf)        
2. Drill 14-3/4” diameter hole into sediment (~120 mbsf) then 10 m into basement        
3. Deploy 10-3/4” casing/land hanger in reentry cone, place shoe at ~125 mbsf        
4. Cement casing shoe/release casing hanger/flush pipe/POOH        
Hole C - RCB core from 130 to 870 mbsf - 750 m into basement     12.8 1.3
1. RCB core basement from 130 to ~870 mbsf        
2. Change bits as required        
3. Condition hole, drop bit on seafloor, and log with triple combo and FMS-sonic        
Subtotal days on site: 20.5      
 
Transit ~1133 nmi to Keelung at 10.5 kt
 
4.5
 
 
Keelung End expedition   6.6 46.8 2.6
  Port call: 5.0 Total operating days: 56.0
  Subtotal on-site: 49.4 Total expedition days: 61.0

All sites pending Environmental Protection and Safety Panel (EPSP) approval. Advanced piston corer temperature tool (APCT-3) measurements to be taken at both primary sites. Nonmagnetic coring equipment to be used when possible (both advanced piston corer [APC] and rotary core barrel [RCB] hole sections). FlexIT orientation tool to be deployed on all APC hole sections starting with Core 1H. Mechanical bit release (MBR) to be run with all RCB bottom-hole assemblies when logging is anticipated. XCB = extended core barrel, DP = dynamic positioning, POOH = pull out of hole, triple combo = triple combination, FMS = Formation MicroScanner.