Table T1. Operations and time estimates for Expedition 353 primary sites.

Site Location Seafloor
depth
(mbrf)
Operations description   Transit (days) Drilling
coring (days)
LWD/MWD
log (days)
Singapore Begin expedition 5.0 Port call days    
      Transit ~16 nmi to W1 @ 6.0 kt   0.1    
      Transit ~2 nmi to W2 @ 6.0 kt   0.0    
      Transit ~9 nmi to W3 @ 6.0 kt   0.1    
      Transit ~151 nmi to W4 @ 10.5 kt   0.6    
      Transit ~705 nmi to AA-4 @ 10.5 kt   2.8    
AA-4B 10°38.03′N 1102 Hole A - APC/XCB core to 422 mbsf   0 2.8 0.0
EPSP to 422 mbsf 93°0.00′E   Hole B - APC/XCB core to 422 mbsf   0 1.9 0.0
      Hole C - APC/XCB core to 422 mbsf   0 2.2 0.0
      Subtotal days on site: 6.8      
      Transit ~9 nmi to AA-2B @ 10.5 kt   0.0    
AA-2B 10°47.41′N 1380 Hole A - APC/XCB core to 738 mbsf   0 4.7 0
EPSP to 738 mbsf 93°0.00′E   Hole B - APC/XCB core to 738 mbsf; wireline log-triple combo/FMS-sonic   0 4.6 1
      Subtotal days on site: 10.3      
      Transit ~652 nmi to BB-7 @ 10.5 kt   2.5    
BB-7 19°5.01′N 1436 Hole A - APC/XCB core to 184 mbsf   0 1.4 0
EPSP to 184 mbsf 85°44.09′E   Hole B - APC/XCB core to 184 mbsf   0 0.8 0
      Hole C - APC/XCB core to 184 mbsf   0 0.9 0
      Subtotal days on site: 3.1      
      Transit ~97 nmi to BB-5 @ 10.5 kt   0.4    
BB-5 17°44.72′N 2506 Hole A - APC/XCB core to 680 mbsf   0 5.2 0
EPSP to 680 mbsf 84°47.25′E   Hole B - APC/XCB core to 680 mbsf; wireline log-triple combo/FMS-sonic   0 5.1 1.0
      Subtotal days on site: 11.4      
      Transit ~89 nmi to BB-2B @ 10.5 kt   0.4    
BB-2B 18°59.82′N 1189 Hole A - APC/XCB core to 184 mbsf   0 1.1 0
EPSP to 184 mbsf 85°37.29′E   Hole B - APC/XCB core to 184 mbsf   0 0.7 0
      Hole C - APC/XCB core to 184 mbsf   0 0.9 0
      Subtotal days on site: 2.6      
      Transit ~862 nmi to N90E-2C @ 10.5 kt   3.5    
N90E-2C 5°23.0041′N 2974 Hole A - APC/XCB core to 350 mbsf   0 2.6 0
Pending EPSP approval 90°21.7099′E   Hole B - APC/XCB core to 350 mbsf   0 2.1 0
      Hole C - APC/XCB core to 350 mbsf; wireline log-triple combo/FMS-sonic   0 2.5 0.8
      Subtotal days on site: 8      
      Transit ~317 nmi to W6 @ 10.5 kt   1.3    
      Transit ~459 nmi to W7 @ 10.5 kt   1.9    
      Transit ~149 nmi to W8 @ 10.5 kt   0.6    
      Transit ~10 nmi to W9 @ 10.5 kt   0.0    
      Transit ~3 nmi to W10 @ 10.5 kt   0.0    
      Transit ~16 nmi to Singapore @ 10.5 kt   0.1    
Singapore End expedition   14.1 39.3 2.9
Port call: 5.0 Total operating days: 56.3
Subtotal on site: 42.1 Total expedition: 61.3