Site
|
Location
|
Seafloor Depth (mbrf)
|
Operations description
|
|
Transit (days)
|
Drilling coring (days)
|
Logging (days)
|
|
Singapore
|
|
Begin Expedition
|
5.0
|
Port call days
|
|
Transit ~1016 nmi to Middle Bengal Fan Site MBF-3A @ 10.5 knots
|
|
4.0
|
|
|
MBF-3A
EPSP Depth
Approved to
1500 mbsf |
08°0.4200’N
|
3629
|
Hole A - APC/XCB core to ~500 mbsf; APC core orientation; formation
temperature measurements (APCT-3) |
|
|
4.7
|
|
088°44.5020’E
|
|
Hole B - Drill down to ~500 mbsf and RCB core to ~1500 mbsf; wireline log
|
|
|
13.7
|
2.6
|
|
|
APC section begins with nonmagnetic core barrels.
|
|
|
|
|
|
Subtotal days on site:
|
21.1
|
|
|
|
|
Transit ~38 nmi to MBF-6A @ 10.5 knots
|
|
0.1
|
|
|
MBF-6A
EPSP Depth
Approved to
500 mbsf |
08°0.4200’N
|
3676
|
Hole A - APC/XCB core to ~300 mbsf; APC core orientation; formation
temperature measurements (APCT-3) |
|
|
3.0
|
|
088°6.6000’E
|
|
|
|
|
|
|
|
APC section begins with nonmagnetic core barrels.
|
|
|
|
|
|
Subtotal days on site:
|
3.0
|
|
|
|
|
Transit ~26 nmi to MBF-2A @ 10.0 knots
|
|
0.1
|
|
|
MBF-2A
EPSP Depth
Approved to
1200 mbsf |
08°0.4200’N
|
3682
|
Hole A - APC/XCB core to ~900 mbsf; APC core orientation; formation
temperature measurements (APCT-3); wireline log |
|
|
7.8
|
1.9
|
087°40.2480’E
|
|
|
|
|
|
|
|
APC section begins with nonmagnetic core barrels.
|
|
|
|
|
|
Subtotal days on site:
|
9.7
|
|
|
|
|
Transit ~29 nmi to MBF-5A @ 10.5 knots
|
|
0.1
|
|
|
MBF-5A
EPSP Depth
Approved to
500 mbsf |
08°0.4200’N
|
3696
|
Hole A - APC/XCB core to ~300 mbsf; APC core orientation; formation
temperature measurements (APCT-3) |
|
|
3.0
|
|
087°10.9020’E
|
|
|
|
|
|
|
|
APC section begins with nonmagnetic core barrels.
|
|
|
|
|
|
Subtotal days on site:
|
3.0
|
|
|
|
|
Transit ~23 nmi to MBF-4A @ 10.5 knots
|
|
0.1
|
|
|
MBF-4A
EPSP Depth
Approved to
500 mbsf |
08°0.4200’N
|
3705
|
Hole A - APC/XCB core to ~300 mbsf; APC core orientation; formation
temperature measurements (APCT-3) |
|
|
3.0
|
|
086°47.8980’E
|
|
|
|
|
|
|
|
APC section begins with nonmagnetic core barrels.
|
|
|
|
|
|
Subtotal days on site:
|
3.0
|
|
|
|
|
Transit ~31 nmi to MBF-1A @ 10.5 knots
|
|
0.1
|
|
|
MBF-1A
EPSP Depth
Approved to
1200 mbsf |
08°0.4200’N
|
3756
|
Hole A - APC/XCB core to ~900 mbsf; APC core orientation; formation
temperature measurements (APCT-3); wireline log |
|
|
8.1
|
1.7
|
086°16.9980’E
|
|
|
|
|
|
|
|
APC section begins with nonmagnetic core barrels.
|
|
|
|
|
|
Subtotal days on site:
|
9.8
|
|
|
|
|
Transit ~470 nmi to Colombo, Sri Lanka @ 10.5 knots
|
|
1.9
|
|
|
|
Colombo, Sri Lanka
|
|
End Expedition
|
|
6.3
|
43.4
|
6.3
|
Port call:
|
5.0
|
Total operating days:
|
56.0
|
|
|
Subtotal on site:
|
49.7
|
Total expedition:
|
61.0
|
|
|
EPSP = Environmental Protection and Safety Panel. APC = advanced piston corer, XCB = extended core barrel, APCT-3 = advanced piston corer temperature tool, RCB = rotary core barrel.