Table T2. Breakdown of operational time while on site during Expedition 302 (ACEX).
Date (2004) |
Time (h) | Comments | ||||||
---|---|---|---|---|---|---|---|---|
T | P | D | W | B | TR | Total | ||
15 Aug | 8.50 | 2.50 | 2.00 | 13 | Chicksan valve broken | |||
16 Aug | 6.00 | 5.00 | 13.00 | 24 | Extended core barrel lost | |||
17 Aug | 24.00 | 24 | BHA lost; chicksan valve broken | |||||
18 Aug | 13.00 | 11.00 | 24 | Repair of chicksan valve | ||||
19 Aug | 9.58 | 14.42 | 24 | |||||
20 Aug | 22.83 | 1.17 | 24 | |||||
21 Aug | 15.83 | 8.17 | 24 | |||||
22 Aug | 24.00 | 24 | ||||||
23 Aug | 10.00 | 14.00 | 24 | |||||
24 Aug | 9.50 | 1.00 | 10.00 | 3.50 | 24 | |||
25 Aug | 10.67 | 1.00 | 1.00 | 11.33 | 24 | Iron roughneck failed; reflective seismics (D) | ||
26 Aug | 3.50 | 4.25 | 16.25 | 24 | Wireline termination failed | |||
27 Aug | 13.50 | 1.50 | 1.75 | 7.25 | 24 | Chicksan valve broken third time | ||
28 Aug | 21.33 | 2.67 | 24 | APC stuck | ||||
29 Aug | 24.00 | 24 | ||||||
30 Aug | 24.00 | 24 | ||||||
31 Aug | 24.00 | 24 | ||||||
1 Sept | 4.75 | 5.42 | 11.67 | 1.00 | 1.17 | 24 | ||
2 Sept | 1.83 | 2.92 | 19.25 | 24 | Logging failed, plugged bit | |||
3 Sept | 23.08 | 0.92 | 24 | |||||
4 Sept | 5.50 | 12.67 | 5.83 | 24 | Equipment frozen | |||
5 Sept | 8.33 | 8.75 | 6.92 | 24 | APC stuck in BHA | |||
6 Sept | 5.00 | 6.50 | 8.00 | 4.50 | 24 | Maintenance of ships; reflective seismics (D) | ||
Totals: | 68.1 | 18.9 | 247.9 | 53.3 | 137.6 | 15.3 | 541 | |
Percent: | 12.6 | 3.5 | 45.8 | 9.8 | 25.4 | 2.8 |
Notes: T = trip time, P = preparation time on rig floor, D = drill time, W = wait for better ice conditions, B = breakdown time, TR = transit time. BHA = bottom-hole assembly, APC = advanced piston corer. Approval was given to start running pipe on Site M0001 at 1100 h on 15 August.