Table T2. Breakdown of operational time while on site during Expedition 302 (ACEX).

Date
(2004)
Time (h) Comments
T P D W B TR Total
15 Aug 8.50 2.50     2.00   13 Chicksan valve broken
16 Aug 6.00     5.00 13.00   24 Extended core barrel lost
17 Aug         24.00   24 BHA lost; chicksan valve broken
18 Aug       13.00 11.00   24 Repair of chicksan valve
19 Aug     9.58   14.42   24  
20 Aug     22.83 1.17     24  
21 Aug     15.83 8.17     24  
22 Aug     24.00       24  
23 Aug     10.00 14.00     24  
24 Aug 9.50 1.00   10.00   3.50 24  
25 Aug 10.67 1.00 1.00   11.33   24 Iron roughneck failed; reflective seismics (D)
26 Aug   3.50 4.25   16.25   24 Wireline termination failed
27 Aug 13.50   1.50   1.75 7.25 24 Chicksan valve broken third time
28 Aug     21.33   2.67   24 APC stuck
29 Aug     24.00       24  
30 Aug     24.00       24  
31 Aug     24.00       24  
1 Sept 4.75 5.42 11.67 1.00 1.17   24  
2 Sept 1.83   2.92   19.25   24 Logging failed, plugged bit
3 Sept     23.08 0.92     24  
4 Sept   5.50 12.67   5.83   24 Equipment frozen
5 Sept 8.33   8.75   6.92   24 APC stuck in BHA
6 Sept 5.00   6.50   8.00 4.50 24 Maintenance of ships; reflective seismics (D)
Totals: 68.1 18.9 247.9 53.3 137.6 15.3 541  
Percent: 12.6 3.5 45.8 9.8 25.4 2.8    

Notes: T = trip time, P = preparation time on rig floor, D = drill time, W = wait for better ice conditions, B = breakdown time, TR = transit time. BHA = bottom-hole assembly, APC = advanced piston corer. Approval was given to start running pipe on Site M0001 at 1100 h on 15 August.