SITE SUMMARIES

Site: SR-1
Priority:
Primary
Position:
47°45.209'N, 127°45.832'W;
approved for 500 m radius surrounding position
Water depth (m):
2611
Target drilling depth (mbsf):
730
Approved maximum penetration (mbsf):
860
Survey coverage:
GeoB 00-466: CDP 557
(track map–Fig. F4; seismic profile–Fig. F5)
Objective:
  • Characterize upper basaltic crust
  • Install long-term borehole observatory (pressure, geochemistry, microbiology)
  • Core and sample sediments
  • Measure downhole formation temperatures
  • Drilling/logging program:
    Deep Hole:
  • Install reentry cone, 20 inch casing to ~75 mbsf;
  • Install 16 inch casing into top of basaltic basement (~280 mbsf)
  • Install 103/4 inch casing through rubble zone to ~380 mbsf
  • RCB core basaltic crust 390 to ~730 mbsf
  • Wireline log with triple combo and FMS-sonic tool strings and UBI and WST-3
  • Packer experiments
  • Install long-term borehole observatory
    Rubble Hole:
  • Install reentry cone, 20 inch casing to ~75 mbsf
  • Install 16 inch casing into top of basaltic basement (~280 mbsf)
  • Install 103/4 inch casing into rubble zone (~325 mbsf)
  • Packer experiments
  • Install long-term borehole observatory
    Sediments:
  • Core sediment section for geochemical and microbiological experiments
  • Temperature measurements (APCT, DVTP)
  • Potential water sampling (WSTP) and core orientation
  • See "Drilling Strategy;" Table T2
  • Nature of rock anticipated:
    Turbidites (sand, silt, clay) and hemipelagic mud, overlying basalt