Table T1. Operations and time estimates for Expedition 332, Site C0010 riserless. (See table notes.)

Site PTD
(mbsf)
Water
depth
(m)
Total
(mbsf)
Operation Estimated
days
Total
days
Number
of cores
C0010
  555 2523.7 555 Move to site, deploy transponders, retrieve corrosion cap:
• Move to site
• Set transponders, ROV survey
• Retrieve corrosion cap
 
0.5
0.5
1.0
 
 
 
2.0
 
Prep for running RBP tool:
• Install guidehorn
• Make up and run RBP tool
• Retrieve RBP and SmartPlug
 
2.0
1.0
1.0
 
 
 
6.0
 
Wireline logging:
• Run 8-1/2 inch bit and scraper assembly to top of cement
• Run guide drill pipe for wireline log
• Run CBL, POOH
 
1.5
0.5
0.5
 

 
8.5
 
Make up and run RBP with probe 2.0 10.5  
Set corrosion cap and retrieve transponders 1.5 12.0  
Contingency:
• Typhoon evacuation
• Equipment downtime
• Wait on weather
 

2.0
1.0
 
 
 
15.0
 
Move to other site 0.5    
Total days: 15.5  

Notes: PTD = proposed total depth. ROV = remotely operated vehicle. RBP = Retrievable Bridge Plug. CBL = cement-bond log. POOH = pull out of hole.