Table T3. Operations plan, alternate sites.

Proposed site Location
(latitude,
longitude)
Seafloor
depth
(mbrf)
Operations description Coring/
drilling
(days)
Log
(days)
GOA15-1A 59° 42.06' N 189 Hole A - APC ~250 mbsf, XCB ~1158 mbsf with APCT3 measurements 4.7 1.5
EPSP depth 143° 7.20' W   and Log w/Triple Combo, FMS Sonic and VSI    
approved to          
1200 mbsf     All APC sections begin with non-magnetic core barrels.    
      Subtotal Days on Site: 6.2    
       
GOA16-2A 58° 46.35' N 3701 Hole A - APC ~200 mbsf, with orientation and APCT3 measurements 1.8  
EPSP depth 144° 30.12' W   Hole B - APC ~200 mbsf 1.4  
approved to     Hole C - APC ~200 mbsf 1.3  
1100 mbsf     Hole D - APC/XCB to 962 mbsf and Log w/ Triple Combo, FMS Sonic, VSI and MMM 7.4 2.1
           
      All APC sections begin with non-magnetic core barrels.    
      Subtotal Days on Site: 14.0    
       
GOAL-16B 58° 46.18' N 3701 Hole A - APC ~200 mbsf, with orientation and APCT3 measurements 1.8  
EPSP depth 144° 29.79' W   Hole B - APC ~200 mbsf 1.4  
approved to     Hole C - APC ~200 mbsf 1.3  
1100 mbsf     Hole D - APC/XCB to 986 mbsf and Log w/ Triple Combo, FMS Sonic, VSI and MMM 7.8 2.2
           
      All APC sections begin with non-magnetic core barrels.    
      Subtotal Days on Site: 14.5    
       
GOAL-18A 56° 57.38' N 4229 Hole A - APC to ~200 mbsf with orientation and APCT3 measurements 2.0  
EPSP depth 147° 8.25' W   Hole B - APC to ~200 mbsf 1.4  
approved to     Hole C - APC/XCB ~780 mbsf and Log w/Triple Combo, FMS Sonic, VSI and MMM 5.9 2.1
856 mbsf     Hole D - APC/XCB to 500 mbsf 4.2  
           
      All APC sections begin with non-magnetic core barrels.    
      Subtotal Days on Site: 15.6    
       
GOA18-1A 56° 56.36' N 4273 Hole A - APC to ~200 mbsf with orientation and APCT3 measurements 2.0  
EPSP depth 147° 22.37' W   Hole B - APC to ~200 mbsf 1.4  
pending     Hole C - APC/XCB ~758 mbsf and Log w/Triple Combo, FMS Sonic, VSI and MMM 5.8 2.3
approval     Hole D - APC/XCB to 500 mbsf 4.2  
           
      All APC sections begin with non-magnetic core barrels.    
      Subtotal Days on Site: 15.7    