Table T2. Operations plan, primary sites.

Proposed site Location
(latitude,
longitude)
Seafloor
depth
(mbrf)
Operations description Transit
(days)
Coring/
drilling
(days)
Log
(days)
Victoria Begin Expedition 5.0 port call days
  Transit ~1037 nmi to KB-2A@ 10.5 knots 4.1    
KB-2A 59° 31.93' N 721 Hole A - APC to ~200 mbsf with orientation   1.1  
EPSP depth 144° 8.03' W   Hole B - APC to ~200 mbsf   0.6  
approved to     Hole C - APC to ~200 mbsf   0.6  
417 mbsf     Hole D - APC/XCB to 400 mbsf and Log w/ Triple Combo, FMS Sonic, VSI and MMM   1.6 1.2
             
      All APC sections begin with non-magnetic core barrels.      
      Subtotal Days on Site: 5.1      
  Transit ~30 nmi to GOAL-15C@ 10.0 knots 0.1    
GOAL-15C 59° 41.34' N 261 Hole A - APC ~250 mbsf, XCB ~1112 mbsf and Log w/ Triple Combo, FMS Sonic, and VSI   4.5 1.5
EPSP depth 143° 12.06' W          
approved to            
1225 mbf     All APC sections begin with non-magnetic core barrels.      
      Subtotal Days on Site: 6.0      
  Transit ~12 nmi to GOAL-17B@ 8.0 knots 0.1    
GOAL-17B 59° 30.44' N 738 Hole A - APC ~250 mbsf, XCB ~1032 mbsf w/ orientation and Log w/ Triple Combo,   4.8 1.5
EPSP depth 143° 2.74' W   FMS Sonic, and VSI      
approved to            
1045 mbsf     All APC sections begin with non-magnetic core barrels.      
      Subtotal Days on Site: 6.3      
  Transit ~62 nmi to GOA16-1A@ 10.5 knots 0.3    
GOA16-1A 58° 46.61' N 3703 Hole A - APC ~200 mbsf, orientation and APCT3 measurements   1.8  
EPSP depth 144° 29.60' W   Hole B - APC ~200 mbsf   1.3  
approved to     Hole C - APC ~200 mbsf   1.3  
1100 mbsf     Hole D - APC/XCB to 978 mbsf and Log w/ Triple Combo, FMS Sonic, VSI and MMM   7.6 2.1
             
      All APC sections begin with non-magnetic core barrels.      
      Subtotal Days on Site: 14.1      
  Transit ~137 nmi to GOA18-2A@ 10.5 knots 0.6    
GOA18-2A 56° 57.60' N 4188 Hole A - APC ~200 mbsf, with orientation and APCT3 measurements   2.0  
EPSP depth 147° 6.60' W   Hole B - APC ~200 mbsf   1.4  
pending     Hole C - APC/XCB ~780 mbsf and Log with Triple Combo, FMS Sonic, VSI and MMM   5.9 2.4
approval     Hole D - APC/XCB to 425 mbsf   3.5  
             
      All APC sections begin with non-magnetic core barrels.      
      Subtotal Days on Site: 15.2      
  Transit ~1032 nmi to Victoria@ 10.5 knots 4.1    
Victoria End Expedition 9.3 38.0 8.7
Port Call Days: 5.0 Total Operating Days: 56.0
Subtotal on Site Days: 46.7 Total Expedition Days: 61.0