Table T23. Event summary of T2P Deployment 11, Hole U1324B.
Event | Time (GMT) |
Event |
---|---|---|
1 | 12:02:00 | Data logger started at 1 Hz |
2 | 12:18:13 | T2P on rig floor |
3 | 12:31:55 | Start lowering T2P downhole, pumps on |
4 | 12:42:00 | Stop at 1068 mbsl, pumps off |
5 | 12:45:46 | Start lowering probe |
6 | 12:50:23 | Stop at 1510 mbsl, pumps off |
7 | 12:56:38 | Start lowering probe |
8 | 12:58:11 | CDS lands in BHA; pumps off |
9 | 13:14:02 | Pulling T2P uphole slowly with wireline |
10 | 13:25:02 | Stop at 1067 mbsl, pumps off |
11 | 13:28:02 | Pulling T2P uphole slowly with wireline |
12 | 13:34:27 | Wireline disconnected from CDS |
13 | 13:38:21 | CDS disconnected from spacer |
14 | 13:40:15 | Spacer disconnected from CDS |
15 | 13:46:40 | T2P out of pipe |
16 | 14:10:36 | Data downloaded from data logger |
Notes: Depth = 593.2 mbsf. Date = 25 June 2005. T2P = temperature/dual pressure probe. CDS = colleted delivery system. BHA = bottom-hole assembly. GMT = Greenwich Mean Time.