Table AT18. Event summary of DVTPP Deployment 17, Hole U1322C, 100 mbsf. (See table notes.)
Event number |
Time (GMT) |
Event description |
---|---|---|
1 | 0152 | Start lowering DVTPP downhole |
2 | 0211 | Stop at mudline for 5 min |
3 | 0216 | Start lowering probe |
4 | Move BHA off BOH | |
5 | 0222 | CDS lands in BHA |
6 | 0233 | Lower bit, start penetration of DVTPP into formation |
7 | 0234 | End of penetration, bit on BOH |
8 | 0235 | Raise BHA 4 m off BOH |
9 | 0405 | Pull probe out of formation and uphole with wireline |
10 | 0409 | Stop at mudline for 5 min |
11 | 0414 | Pull DVTPP uphole with wireline |
Notes: Measurements taken 1 July 2005. GMT = Greenwich Mean Time, DVTPP = Davis-Villinger Temperature-Pressure Probe, BHA = bottom-hole assembly, BOH = bottom of hole, CDS = colleted delivery system.