Table T1. Operation plan and time estimate for Expedition 316. (See table notes.)
Hole |
PTD (mbsf) |
Water depth (m) |
Total (mbsl) |
Operation |
Estimated days |
Number of cores |
---|---|---|---|---|---|---|
Proposed Site NT1-03 | ||||||
B | 600 |
3955
|
4555
|
Move to site, preparation for drilling (BHA, etc.) |
1.0
|
|
RIH HPCS/ESCS |
0.5
|
|||||
Core with HPCS/ESCS to 600 mbsf:- HPCS and ESCS to PTD; if cannot reach PTD, go to Hole C- Require core orientation- Hole size: 11-7/16 inch- Temperature measurement every 50 m by APCT-3 or DVTP (0.5 days) |
5.5
|
63
|
||||
POOH, lay out HPCS/ESCS |
1.0
|
|||||
8.0
|
||||||
C | 950 |
3955
|
4905
|
Move to Hole C, RIH RCB |
0.5
|
|
Drill to 600 mbsf by RCB:- If Hole A <PTD, start core at Hole A refusal depth(take overlapping cores in Hole C)- Limit progress to 400 m per day to maintain good hole- Hole size: 9-7/8 inch |
1.5
|
|||||
Core with RCB to 950 mbsf:- Take 400 m of core by RCB- Take overlapping core of Hole B- Penetration rate: 100 m per day |
3.5
|
37
|
||||
Displace with weighted mud, POOH, lay out RCB assembly |
1.0
|
|||||
6.5
|
||||||
Proposed Site NT2-01 | ||||||
B | 600 |
2391
|
2991
|
Move to site (13 nmi), RIH HPCS/ESCS assembly |
1.0
|
|
Core with HPCS/ESCS to 600 mbsf:- HPCS/ESCS to PTD; if cannot reach PTD, go to Hole C- Require core orientation- Hole size: 11-7/16 inch- Temperature measurement every 50 m by APCT-3 or DVTP |
5.5
|
64
|
||||
POOH, lay out HPCS/ESCS assembly |
0.5
|
|||||
Retrieve guidehorn |
0.5
|
|||||
7.5
|
||||||
C | 1000 |
2391
|
3391
|
Move to Hole C, set riserless wellhead with 20 inch casing |
2.0
|
|
Install guidehorn |
0.5
|
|
||||
RIH RCB assembly |
0.5
|
|
||||
Drill with RCB to 600 mbsf:- If Hole B <PTD, take core from Hole A refusal depth- Limit progress to 400 m per day to maintain good hole- Hole size: 9-7/8 inch |
1.5
|
|
||||
Core with RCB to 1000 m- Take 400 m core by RCB- Take overlapping core of Hole A- Penetration rate: 100 m per day |
4.0
|
43
|
||||
POOH |
0.5
|
|
||||
RIH hole opener |
0.5
|
|
||||
Open hole to 17-1/2 inch (penetration rate: 400 m per day) |
2.5
|
|
||||
Wiper trip, spot high-viscosity mud, POOH stand-back hole opener |
1.0
|
|
||||
Run 13-3/8 inch casing |
1.0
|
|
||||
Cement with POOH running tool |
0.5
|
|
||||
Retrieve guidehorn, etc. |
1.0
|
|||||
15.5
|
||||||
37.5
|
||||||
0.5
|
||||||
0.0
|
||||||
2.0
|
||||||
40.0
|
||||||
9.5
|
||||||
49.5
|
Notes: PTD = proposed total depth. HPCS = hydraulic piston coring system, ESCS = extended shoe coring system, RCB = rotary core barrel, BHA = bottom-hole assembly. RIH = run in hole, POOH = pull out of hole. DVTP = Davis-Villinger Temperature Probe, APCT-3 = third-generation advanced piston corer temperature tool.