Previous   |    Close   |    Next

Table AT20. Event summary of DVTPP Deployment 19, Hole U1322C, 238 mbsf. (See table notes.)

Event
number
Time
(GMT)
Event
description
1 1901 Start lowering DVTPP downhole
2 1923 Stop at mudline for 5 min
3 1928 Start lowering probe
4 1928 Moving BHA to 11 m off BOH
5 1934 CDS lands in BHA
6 1944 Lower bit, start penetration of DVTPP into formation
7 1945 End of penetration, bit on BOH
8 1946 Raise BHA 2 m off BOH
9 1948 Lower BHA back to BOH
10 1950 Raise BHA 6 m off BOH
11 2118 Pull probe out of formation and uphole with wireline
12 2124 Stop at mudline for 5 min
13 2128 Pull DVTPP uphole with wireline

Notes: Measurements taken 1 July 2005. GMT = Greenwich Mean Time, DVTPP = Davis-Villinger Temperature-Pressure Probe, BHA = bottom-hole assembly, BOH = bottom of hole, CDS = colleted delivery system.

Previous   |    Close   |    Next   |    Top of page