Table AT41. Event summary of T2P Deployment 23, Hole U1322C, 150.0 mbsf. (See table notes.)
Event number |
Time (GMT) |
Event description |
---|---|---|
1 | Start data logger at 1 Hz | |
2 | 0651 | T2P on rig floor |
3 | 0701 | Start lowering T2P downhole, pumps on |
4 | 0709 | Stop at 491 mbsl, pumps off |
5 | 0712 | Start lowering probe |
6 | 0717 | Stop at 741 mbsl, pumps off |
7 | 0719 | Start lowering probe |
8 | 0729 | Stop at 1321 mbsl, pumps off |
9 | 0743 | Start lowering probe |
10 | 0752 | Stop at 1459 mbsl, pumps off |
11 | 0754 | Start lowering probe |
12 | 0758 | CDS lands in BHA, pumps off |
13 | 0758 | Start penetration of T2P into sediment |
14 | 0802 | End of T2P penetration, bit 1 m off BOH |
15 | 0803 | Raise BHA 4.0 m off BOH |
16 | 0905 | Pull T2P uphole slowly with wireline |
17 | 0912 | Stop at 1321 mbsl, pumps off |
18 | 0914 | Pull T2P uphole slowly with wireline |
19 | 0924 | Stop at 741 mbsl, pumps off |
20 | 0926 | Pull T2P uphole slowly with wireline |
21 | 0932 | Stop at 491 mbsl, pumps off |
22 | 0934 | Pull T2P uphole slowly with wireline |
23 | Download data from data logger |
Notes: Measurements taken 1 July 2005. GMT = Greenwich Mean Time, T2P = temperature/dual pressure probe, CDS = colleted delivery system, BHA = bottom-hole assembly, BOH = bottom of hole.