IODP

doi:10.2204/iodp.sp.341S.2013

Site summaries (continued)

Hole 858G re-CORK

Priority: Primary
Position: 48° 27.360’N, 128°42.531’W
Water depth (m): 2415
Target drilling depth (mbsf): No drilling planned; only CORK replacement
Approved maximum penetration (mbsf): Not applicable
Survey coverage (track map; seismic profile): See ODP Leg 139 and 169 Initial Reports (Davis, Mottl, Fisher, et al., 1992; Fouquet, Zierenberg, Miller, et al., 1998)
Objective(s): Replace CORK observatory
Drilling program: (1) Retrieve Leg 169 CORK, (2) install new CORK (see Table T2)
Downhole measurements program: Installation of long-term CORK observatory including measurements of temperature and pressure
Nature of rock anticipated: Not applicable