Priority:
|
Primary
|
Position:
|
47°45.210′N, 127°45.833′W
|
Water depth (m):
|
2611
|
Target drilling depth (mbsf):
|
Not applicable; reoccupy existing borehole; no new penetration
|
Approved maximum penetration (mbsf):
|
Not applicable; reoccupy existing borehole; no new penetration
|
Survey coverage:
|
GeoB00-466: CDP 557 (Track Map Fig. F2, Seismic Profile Fig. F4) |
Objective:
|
Long-term monitoring of pressure, geochemistry, and microbiology
|
Drilling and Logging program:
|
Conduct remedial cementing operations
See "Operations plan/drilling strategy" and Table T3 |
Nature of rock anticipated:
|
Not applicable; reoccupy existing borehole; no new penetration
|