Strategy/Drilling plan
Details regarding the original drilling plan are available in Mori et al. (2012), but the general planned sequence of drilling was as follows:
-
Drilling the pilot hole with logging while drilling (LWD)/measurement while drilling (MWD) to total depth (TD), planned for ~900 mbsf;
-
Running casing and a completion assembly (including long-term temperature monitoring with a string of autonomous data loggers) in the LWD/MWD hole to ~900 mbsf (casing to 50 m below fault, ~900 m);
-
Drilling a second hole with the rotary core barrel (RCB) and center bit to ~500 mbsf and continuation with RCB coring to ~900 mbsf; and
-
Running casing and a completion assembly for the second hole (including long-term temperature and pressure monitoring with the telemetered sensor string) to ~900 mbsf (casing to 50 m below fault, ~900 m).